US20070094043A1 - Energy service business method and system - Google Patents
Energy service business method and system Download PDFInfo
- Publication number
- US20070094043A1 US20070094043A1 US11/583,883 US58388306A US2007094043A1 US 20070094043 A1 US20070094043 A1 US 20070094043A1 US 58388306 A US58388306 A US 58388306A US 2007094043 A1 US2007094043 A1 US 2007094043A1
- Authority
- US
- United States
- Prior art keywords
- energy
- data
- saving
- measures
- curtailment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
- 238000000034 method Methods 0.000 title description 35
- 238000005265 energy consumption Methods 0.000 claims abstract description 52
- 238000004519 manufacturing process Methods 0.000 claims abstract description 35
- 230000000875 corresponding effect Effects 0.000 claims abstract 4
- 230000002596 correlated effect Effects 0.000 claims abstract 2
- 238000004364 calculation method Methods 0.000 claims description 15
- 230000000694 effects Effects 0.000 description 55
- 238000012423 maintenance Methods 0.000 description 23
- 238000007726 management method Methods 0.000 description 17
- 230000008569 process Effects 0.000 description 16
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 14
- 238000012986 modification Methods 0.000 description 12
- 230000004048 modification Effects 0.000 description 12
- 238000012544 monitoring process Methods 0.000 description 12
- 238000004134 energy conservation Methods 0.000 description 11
- 239000007789 gas Substances 0.000 description 10
- 230000006872 improvement Effects 0.000 description 10
- 238000012545 processing Methods 0.000 description 10
- 238000010586 diagram Methods 0.000 description 8
- 238000003860 storage Methods 0.000 description 8
- 239000002918 waste heat Substances 0.000 description 8
- 239000002826 coolant Substances 0.000 description 7
- 238000001816 cooling Methods 0.000 description 7
- 238000009826 distribution Methods 0.000 description 6
- 238000011156 evaluation Methods 0.000 description 6
- 239000000446 fuel Substances 0.000 description 6
- 238000004891 communication Methods 0.000 description 5
- 230000004044 response Effects 0.000 description 5
- 238000004378 air conditioning Methods 0.000 description 4
- 239000002131 composite material Substances 0.000 description 4
- 239000000498 cooling water Substances 0.000 description 4
- 230000005611 electricity Effects 0.000 description 4
- 238000009434 installation Methods 0.000 description 4
- 230000007257 malfunction Effects 0.000 description 4
- 238000005259 measurement Methods 0.000 description 4
- 238000011084 recovery Methods 0.000 description 4
- 238000003745 diagnosis Methods 0.000 description 3
- 230000006870 function Effects 0.000 description 3
- 230000008520 organization Effects 0.000 description 3
- 230000008439 repair process Effects 0.000 description 3
- 238000012546 transfer Methods 0.000 description 3
- 230000003247 decreasing effect Effects 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 239000006185 dispersion Substances 0.000 description 2
- 238000013213 extrapolation Methods 0.000 description 2
- 239000012530 fluid Substances 0.000 description 2
- 238000011835 investigation Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 238000004321 preservation Methods 0.000 description 2
- 238000012827 research and development Methods 0.000 description 2
- 230000001131 transforming effect Effects 0.000 description 2
- 238000012795 verification Methods 0.000 description 2
- 238000010792 warming Methods 0.000 description 2
- 230000003936 working memory Effects 0.000 description 2
- 238000006243 chemical reaction Methods 0.000 description 1
- 230000006866 deterioration Effects 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- -1 heat Substances 0.000 description 1
- 230000005764 inhibitory process Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 239000003921 oil Substances 0.000 description 1
- 238000011017 operating method Methods 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 238000002310 reflectometry Methods 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 230000000717 retained effect Effects 0.000 description 1
- 239000002912 waste gas Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0637—Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
- G06Q10/06375—Prediction of business process outcome or impact based on a proposed change
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
- H02J3/008—Circuit arrangements for AC mains or AC distribution networks involving trading of energy or energy transmission rights
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/70—Smart grids as climate change mitigation technology in the energy generation sector
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P80/00—Climate change mitigation technologies for sector-wide applications
- Y02P80/10—Efficient use of energy, e.g. using compressed air or pressurized fluid as energy carrier
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/80—Management or planning
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S50/00—Market activities related to the operation of systems integrating technologies related to power network operation or related to communication or information technologies
- Y04S50/10—Energy trading, including energy flowing from end-user application to grid
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S50/00—Market activities related to the operation of systems integrating technologies related to power network operation or related to communication or information technologies
- Y04S50/16—Energy services, e.g. dispersed generation or demand or load or energy savings aggregation
Definitions
- the present invention relates to energy service business method and system.
- the invention permits easier introduction of energy-saving measures by creating the following energy service businesses.
- a first form of management is characterized in that the investment cost for energy-saving measure is derived from contribution of funds by energy service enterprises and energy conservation effect, i.e., curtailment of the energy costs. More specifically, the process comprises the steps of applying energy-saving measures to object facilities at the cost of an energy service enterprise, measuring the energy consumption after taking energy-saving measures, and calculating the amount of curtailment of the energy costs by comparing the thus measured value with the energy consumption before taking the energy-saving measures previously stored in a database, and allowing the energy service enterprise to receive at least a part of the amount of curtailment.
- the customer not required to make an equipment investment for taking energy-saving measures and plan collection thereof, is easier to introduce energy-saving measures. As a result, introduction of energy-saving measures is encouraged, and inhibition of global warming and preservation of environments are promoted.
- the energy consumption before taking energy-saving measures together with attribute data of variable factors of the energy consumption, in the database, measuring the energy consumption after taking the energy-saving measures, together with the attribute data, and compare the measured value with the energy consumption before taking the energy-saving measures corresponding to the measured attribute data.
- the attribute data is characterized by being at least one of temperature, humidity and load quantity of the object equipment. It is desirable to retrieve a plurality of past data corresponding to a plurality of attribute data approximating the measured attribute data, perform calculation for estimating past data corresponding to the measured attribute data from the plurality of past data, and compare the measured data with the calculated past estimated data.
- the amount received by the energy service enterprise should preferably be determined with reference to the operating hours or the operating rate of the object equipment.
- the energy service enterprise provides maintenance or improvement without compensation of the equipment to which the energy saving is applied so as to satisfy the reference value.
- the amount received by the energy service enterprise is, when the total amount of the fixed costs such as depreciation and tax and tariffs for a single fiscal year for taking energy-saving measures and the variable costs such as maintenance cost of energy-saving equipment is Q, the annual amount of curtailment of energy costs is P, and ⁇ and ⁇ are positive coefficients (where ⁇ > ⁇ ):
- the amount collected by the energy service enterprise is determinable on the basis of the operating hours or the operating rate of the energy-saving object equipment or the energy-saving equipment.
- the energy service enterprise can receive an amount of collection in response to an amount of energy cost curtailment calculated periodically (every three months, for example).
- the energy service enterprise When the quantity of energy curtailment is smaller than an assured value, the energy service enterprise performs maintenance of the energy-saving equipment or improvement thereof so as to satisfy the assured value.
- the customer and the energy service enterprise may share the installation cost of the energy-saving equipment to install the same.
- the energy service enterprise receives an amount calculated by distributing the amount of energy cost curtailment in accordance with the share thereof.
- a second form of management of the invention is characterized in that the energy service enterprise drafts a plan and executes energy-saving measures and assures an energy-saving effect, i.e., an amount of energy cost curtailment, irrespective of whether or not the energy service enterprise contributes investment funds for the energy-saving measures.
- this process comprises the steps of drafting energy-saving measures by the energy service enterprise or a related organization thereof; assuring, under certain conditions, a quantity of curtailment of energy consumption available when taking energy-saving measures in accordance with the thus drafted measures; measuring the energy consumption after taking the energy-saving measures; calculating the amount of curtailment of energy costs by comparing the thus measured value with the energy consumption before taking the energy-saving measures previously stored in a database, and periodically confirming the assured quantity of curtailment.
- the certain conditions are conditions determined as to variable factors having an important effect on curtailment of the energy consumption such as the operating rate or operating hours, operating conditions (production quantity, frequency of batch processing, etc.) of the energy-saving object equipment.
- the certain conditions can have ranges.
- Weather conditions temperature, humidity
- weather conditions which have an important effect on the energy-saving, can be coped with by using past data obtained under the same conditions. If past data under the same conditions are unavailable, approximate data are used through interpolation or extrapolation.
- the energy service enterprise should preferably perform maintenance of the energy-saving equipment or improvement thereof so as to satisfy the assured value.
- the method of business as described above can be achieved by adopting a system comprising a database which stores past data about the energy consumption before taking energy-saving measures; measuring means which measures the energy consumption after taking energy-saving measures; and calculating means which calculates the energy curtailment quantities before and after taking energy- saving measures by incorporating measurement data measured by the measuring means via a communication line and comparing the measurement data and the past data stored in the database.
- the past data in the database are stored together with attribute data regarding variable factors of the energy consumption.
- the attribute data represents at least one of temperature, humidity and load quantity of an energy-saving object equipment.
- the calculating means calculates the amount of curtailment of the energy costs on the basis of the energy curtailment quantity, and issues a bill demanding payment of an amount obtained by multiplying the amount of curtailment by a predetermined ratio.
- FIG. 1 illustrates a flowchart of energy-saving measures of an embodiment of the energy service business method of the present invention
- FIG. 2 is a conceptual view illustrating a form of contract of the energy service business method of the invention
- FIG. 3 illustrates the concept of allocation of profit under the energy-saving effect in the energy service business method of the invention
- FIG. 4 is a descriptive view of an example explaining energy-saving object facilities and an energy-saving equipment
- FIG. 5 is a flowchart illustrating a detailed procedure for evaluation of the flow shown in FIG. 1 and setting of years under contract;
- FIG. 6 is a diagram explaining the relationship between the annual operating hours and annual expenses/accrued costs of an energy-saving equipment
- FIG. 7 is a flowchart illustrating the calculating procedure of the annual profit of the flow shown in FIG. 1 and expenses of the energy service enterprise;
- FIG. 8 is a flowchart illustrating contents and procedure of management control of the energy-saving equipment in the flow shown in FIG. 1 ;
- FIG. 9 illustrates (A) and (B), two examples of determination of the sharing ratio of the energy-saving effects
- FIG. 10 is a configuration diagram illustrating an embodiment of the management control system of the energy service business method
- FIG. 11 is a system configuration diagram of an embodiment of a co-generator
- FIG. 12 illustrates generating output and efficiency properties of a co-generator
- FIG. 13 is a system diagram of a refrigerator based on inverter driving.
- FIG. 14 is a diagram illustrating the relationship between input energy (electric input) and output energy (refrigerator output) of an inverter-driven refrigerator and a refrigerator without inverter;
- FIG. 15 is a diagram showing a relationship of energy consumption and production quantity.
- FIG. 1 illustrates an embodiment of flowchart of the energy-saving measures in an energy service business method.
- Energy-saving object facilities include, all types of equipment, facilities, machines, and apparatuses consuming energy such as various production facilities, utility facilities (such as electric power, gas, heat, air and water), general buildings (such as office buildings, hospitals and public facilities).
- Utility facilities such as electric power, gas, heat, air and water
- general buildings such as office buildings, hospitals and public facilities.
- Energy-consuming, in addition to electric power, gases, and heat (cold and warm), include utilities such as water, air and the like.
- object facilities Investigation of the current status of energy-saving object facilities (hereinafter simply referred to as “object facilities”) covers timing of introduction of object facilities, status of facilities such as operating hours or number of days, and energy consumption.
- a plan of energy-saving measures is drafted.
- a basic plan of energy-saving measures by setting basic conditions for the installation space for the energy-saving facilities, amount of investment, electric power under contract, number of years of depreciation, impact on environments, and future expansion plan.
- Electric power under contract is set because the power unit price varies with the electric power under contract.
- the energy-saving measures include replacement of existing facilities by energy-saving type new facilities, addition of energy-saving facilities, proposal of maintenance for energy conservation, and proposal of management and control of facilities for energy saving.
- the operating cost, equipment cost, maintenance expenses and personnel cost are tentatively calculated.
- the curtailment effect of CO 2 by energy saving is tentatively calculated to approximately evaluate validity of the modification plan. That is, the increase in various costs required for introduction of energy-saving facilities and the cost curtailment effect of energy conservation are macroscopically and comparatively examined, and the validity of the basic modification plan is assessed regarding the presence of troubles caused by introduction of the energy-saving facilities.
- the current energy consumptions are measured for the object facilities, and detailed energy diagnosis is performed.
- This diagnosis gives past data used when calculating the energy-saving effect, as described later.
- the energy consumptions of the object facilities vary with the load such as the production quantity of the object facilities, operating hours or operating rate, weather conditions (temperature, humidity), season, and day or night. Therefore, in order to calculate the energy-saving effect by comparing energy consumptions before and after modification, it is necessary to collect energy consumption data for the individual object facilities before modification to be compared, together with attribute data such as load on the object facilities, temperature and humidity, for the longest possible period of time, and prepare a database of past data before modification.
- a concrete energy-saving measures are planned on the basis of the database prepared in step S 15 .
- a method of energy-saving measures comprises the steps, for example, of investigating the pattern of daily power consumption or heat energy consumption for the object equipment, and when the daytime power consumption is very small as compared with the night one, storing electric energy in the night in an ice heat accumulating system, an accumulator, or a power storage equipment, releasing the same in the daytime, and balancing the power between day and time, thereby curtailing the power cost. It is necessary to examine introduction of energy-saving facilities generating electric power and heat by burning a fuel such as oil or gas such as a composite generator (co-generator). Furthermore, the driving motor of a pump or a fan is converted into inverter control, and energy conservation is achieved by controlling the number of revolutions of the motor in response to a load thereof. Various often energy-saving measures are proposed.
- the curtailment effort of the energy consumption is tentatively calculated for the care when these energy-saving measures are taken.
- the effect thereof on environments is taken into account, and at the same time, labor saving and achievement of a higher efficiency are accomplished for the control of the energy facilities.
- the evaluation criterion is whether or not the investment funds for the energy-saving measures can be collected within an appropriate number of years (for example, within ten years at the latest).
- the customer and the energy service enterprise consider entering into a contract specifying that number of years as the years under contract and the customer shall pay a part of the curtailed amount of energy cost under the energy-saving effect to the energy service enterprise.
- a contract form as shown in the conceptual view illustrated in FIG. 2 is adopted.
- the investment cost required for energy-saving measures applied to the energy-saving object facilities of the customer I i.e., the modification cost including the installation cost of the energy-saving-equipment is borne by the energy service enterprise II.
- the energy service enterprise III is financed by a financial institution III with investment funds as required.
- the energy-saving enterprise III enters with the customer I into a contract for sharing the amount of curtailed energy cost achieved under the energy-saving effect a certain ratio with the customer.
- a concrete example of the distribution contract will be described later.
- the customer I and the energy service enterprise II share the amount of curtailment of the energy cost after taking the measures from the energy cost before taking the measures.
- the energy service enterprise thus carries out business with the dividend paid by the customer as income. More particularly, the energy service enterprise carries out business by appropriating the dividend income for repayment of the loan financed by the financial institution III, and on the other hand, for management and control (verification, maintenance and improvement) of the energy-saving facilities.
- the distribution ratio of dividend may be determined on the basis of the operating hours or operating rate of the energy-saving facilities. Since the energy-saving effect largely varies with the operating rate among others, the contract should preferably set forth that the distribution ratio for the energy service enterprise II shall be reduced when the operating rate is high. A concrete example of distribution will be described later.
- the energy service enterprise or a related organization thereof conducts a detailed design of the energy-saving measures under the contract, and executes the work including installation of energy-saving equipments and modification of existing facilities.
- the energy service enterprise carries out management and control of services for the energy-saving measures including surveillance of the energy-saving equipment, verification of the energy-saving effects, maintenance and improvement. More specifically, the energy consumption after taking energy-saving measures, and voltage, current, flow rate of fuel, flow rate of a fluid such as coolant and temperature necessary for calculating the energy consumption are periodically (for example, every 15 minutes or every hour) measured, and recorded as measured data. Attribute data such as load on the object facilities, temperature and humidity are measured in parallel with this, and recorded together with the measured data including the energy consumption. The quantity of energy curtailment is calculated by comparing the same or substantially the same measured with past data previously stored in the database.
- the amount of curtailed energy cost is calculated on the basis of the thus calculated quantity of curtailed energy and the energy unit price set forth in the contract.
- Dividend is calculated periodically (for example, monthly, every three to 12 months), on the basis of this amount of curtailment. The energy-saving effect is reported to the customer, and payment of the dividend is demanded.
- the energy service enterprise When the quantity of energy curtailment is under a predetermined reference value of an assured value, on the contrary, the energy service enterprise provides maintenance or improvement of the energy-saving equipment without compensation so as to satisfy the reference value. Control is performed so as to satisfy the assured value or the reference value of the quantity of curtailed energy by appropriately monitoring the data recorded through measurement of the energy consumption after taking the energy-saving measures, determining whether or not the energy-saving equipment displays, determining performance, and applying maintenance or the like as required.
- FIG. 4 illustrates a concrete example of energy-saving measures to be examined in step S 12 or S 16 shown FIG. 1 .
- the object facilities shown in FIG. 4 represent the case of research institute. In view of the basic fact that energy consumption is considerably smaller than that in daytime, the following energy-saving measures are examined.
- Electric power storage facilities 1 :
- Power charges are reduced by storing night electric power of a lower rate, and releasing the same at the daytime peak of power consumption, thus leveling the power consumptions.
- reducing the contract power reduces the power unit price.
- Ice heat accumulating system 2
- Power charges can be reduced by manufacturing ice by use of night electric power, and utilizing the low temperature of ice for air conditioning during daytime, thus reducing the daytime power consumption through leveling of the power consumptions.
- the power consumption can be leveled between night and daytime by generating power from sun light during the daytime.
- Power consumptions are leveled between night and daytime by generating power through driving of a prime mover such as an engine by a gas or oil fuel, and on the other hand, waste heat of prime mover is used for air conditioning and hot water supply.
- a prime mover such as an engine by a gas or oil fuel
- waste heat of prime mover is used for air conditioning and hot water supply.
- use of a dispersion type composite generating system permits improvement of energy efficiency and reduction of driving noise.
- Cooling source (cooling tower) 5 Cooling source (cooling tower) 5 :
- the capacity of pumps for cooling water and cold water can be reduced and the power consumption is curtailed by improving the cooling efficiency of the cooling tower and increasing the temperature difference between entry and exit of cooling water and cold water.
- Power saving can be achieved by changing control of driving motors for air conditioner fans and cold water pumps into inverter control, and reducing the number of revolutions in response to the air conditioning load.
- Power consumption can be reduced by reducing loss (no-load loss, load loss) of the power receiving and transforming machines such as transformers.
- Power consumption is saved by operating fluorescent lumps with a high-frequency inverter. Contrivances are made in lighting so as to use sunlight during daytime. Illuminance is improved by pasting a high-reflectivity film to the reflector.
- the operating status of the facilities and the energy consumption is monitored, and improvement is examined for facilities showing water of energy or a poor efficiency, if any.
- Processed water discharged from a water treatment equipment 10 is reused as so-called intermediate water, thereby effectively utilizing water resources. Efforts are made also to reduce the quantity of dust and waste.
- the amount of curtailment is calculable by multiplying the quantities of curtailed energy before and after taking the energy-saving measure by an energy unit price: a represents an amount of curtailed energy cost per unit operating time (curtailment coefficient); and H, annual operating hours of the object equipment.
- the mount of curtailment K increases according as the annual operating hours of the energy-saving equipment H is longer.
- the relationship between the annual cost/accrued costs and the annual operating hours is as shown in FIG. 6 .
- Step S 23 It is determined whether of not the ratio of P to Q determined in Step S 23 satisfies the range of the following formula: 1.08 ⁇ P/Q ⁇ 1.15 If this formula is not satisfied, the process advances to step S 26 .
- step S 26 If P/Q is under the above-mentioned range, the contract number of years n is extended for another one year (S 26 ), and returning to step S 22 via step S 27 , and the aforementioned processing is executed again.
- the examination is discontinued (step S 27 ).
- step S 28 If P/Q is within the above-mentioned range in the determination in step S 25 as a result of repetition of processing, the number of contract years N is determined in step S 28 .
- steps S 22 and S 23 will now be described with reference to the flow shown in FIG. 7 .
- the depreciation cost ( 1 ) for each fiscal year is calculated on the assumption that the costs for the energy-saving measures are to be depreciated in the number of contract years. Necessary data in this calculation include the personnel cost, materials cost, processing cost and the increment ratios thereof, which are on stored in the database.
- Data necessary for this calculation include fixed asset tax, and excise, which are stored in the database.
- the maintenance cost ( 3 ) is calculated in step S 34 . That is, costs required for maintenance, inspection and modification necessary for assuring or keeping the energy-saving effect. Data necessary for this calculation include personnel cost, materials cost, processing cost and increment ratios thereof, which are stored in the database.
- the amount of curtailment which represents the energy-saving effect after taking the energy-saving measures is calculated on the basis of the energy consumptions calculated in step S 35 .
- the amount of curtailment in this case can be calculated in units of a month, or three to 12 months.
- Data necessary for this calculation include charge data of electricity, gas, oil and water and tax data such as excise, which are stored in the database.
- step S 37 it is determined whether or not the energy-saving effects of step S 36 have been added up for a full year. If not, one hour is added to t in step S 38 , and returning to step S 34 , the process is repeated.
- step S 37 the annual project (energy-saving effect) p and the expenses Q for the energy service enterprise are calculated on the basis of the amounts of curtailed energy K before and after taking the energy-saving measures, and the process domes to an end.
- FIG. 8 illustrates contents and procedure of management control after startup of operation of the energy-saving equipment upon the completion of detailed design and modification work of the energy-saving measures under the contract (S 18 ) entered into upon agreement between the customer and the energy service enterprise, as represented in the concrete flow of step S 20 shown in FIG. 1 .
- the process is executed at intervals of a certain period of time ( ⁇ t: for example, every 15 minutes or every hour): preparation and submission of a report to the customer as an end, the time counter t is reset to 0, and repetition is started.
- ⁇ t for example, every 15 minutes or every hour
- a remote information control server executing the process of FIG. 8 is provided, for example, on the energy service provide side. Therefore, measured data necessary for calculating the energy conservation for each machine are measured via a monitor provided on the energy-saving object facilities and the energy-saving equipments, collected by a data collecting and transmitting unit, and transferred to the remote information control server.
- the measured data include, in addition to quantities of energy consumed electric power and fuel quantities such as gas and oil for each equipment, physical quantities such as temperature, heat and flow rate regarding the energy consumption.
- Machines include a motor, a pump, a fan, an air compressor, a compressive refrigerator, a suction type refrigerator, and a co-generator (composite generator) and other prime movers.
- load data having an effect on the energy consumption such a temperature, humidity and production quantity are measured as attribute data and collected and transferred.
- the measured data including the thus transferred attribute data are once stored, for example, in a working memory of the remote information control server of a database. Energy consumptions of the individual machines are calculated on the basis of the measured data thus stored in the database.
- the past energy consumptions or past data of the corresponding machine are retrieved from the database, and the energy-saving effect, i.e., the quantity of energy curtailment is tentatively calculated by comparing these data.
- step S 43 Data are compared so as to see whether or not the energy-saving effect calculated in step S 43 reaches the quantity of initially planned effect. If the planned value is not reached by the energy-saving effect, the process proceeds to steps S 45 and S 46 , and when it is reached, the process goes to step S 47 .
- step S 48 it is determined for all the machines whether or not the energy-saving effect has been calculated. If not, the process returns to step S 42 , and the process of tentatively calculating the energy-saving effect for each machine is repeated. Upon the completion of tentative calculation of the energy-saving effect for all the machines, the process advances to step S 48 .
- the quantities of energy saving i.e., the energy-saving effects for all the machines are added up in this step S 48 to calculate the quantity of energy curtailment resulting from the energy-saving measures.
- step S 48 the planned value of the quantity of energy curtailment agreed upon between the energy service enterprise and the customer is compared for evaluation with the quantity of energy curtailment calculated in step S 48 .
- step S 51 the reason of non-satisfaction is retrieved in step S 51 . For example, examination is made by, for example, comparing characteristics of the corresponding machines with the initially planned characteristics. If it is satisfied, n the other hand, the process proceeds to step S 52 , and the time counter is put forward by ⁇ t.
- step S 55 it is determined whether or not it is a report timing to the customer as set forth in the contract (for example, a month, three months, six months and a year). If not the report timing, the calculated result is stored as result data in the database, returning to step S 42 to repeat the process. It is a report timing, the process advances to step S 55 .
- a bill is prepared on the basis of the result of tentative calculation of the energy-saving effect.
- a amount based on a ratio corresponding to the energy-saving effect as get forth under the contract is demanded.
- An example of determination of this amount will be described on the assumption that the energy service enterprise is responsible for payment of the costs necessary for the energy-saving measures. As described above with reference FIG.
- FIG. 9 (A) illustrates example of shares.
- Setting a reference value or a planned value of the annual operating rate at such a point leads to an increase in the number of contract years, i.e., the number of years required for collecting the costs. This is therefore unrealistic.
- the absolute value of the amount of curtailed energy is also smaller. When distributing an amount of curtailed energy cost (annual profit), therefore, an amount over a certain amount of curtailment should be set as a planned value.
- the share of the energy service enterprise is larger because the enterprise is responsible for paying all the costs for the energy-saving measures, and this forms one of the features of the method of the present invention.
- the energy service enterprise receives payment of a certain amount as a minimum guarantee for the necessity to collect the invested funds. This amount should preferably be an amount corresponding to the total of the depreciation ( 1 ), the expenses ( 2 ) and the maintenance cost ( 3 ) as shown in FIG. 6 , but it depends upon agreement between the parties.
- FIG. 9 (B) shows another example of distribution.
- the share of the energy service enterprise is increased to X3, as compared with the share of X when the effect is equal to the expected value, to serve as a bonus.
- the share of the enterprise may be decreased even to X4 in some cases.
- the energy service enterprise has intention to repay an amount Z to the financial institution on the basis of the share X, and the share is increased to X3, the energy service enterprise puts the increment of share Z3 aside provisionally, and when the share becomes X4, on the contrary, manages the business so as to provisionally loan the decrement of share Z4.
- the energy service enterprise prepares a result report of energy conservation and submits the same to the customer together with a bill, the process returning to step S 41 to repeat the steps.
- FIG. 10 illustrates an embodiment of the management control system of the aforementioned energy service business method.
- the management control system provided in a building or a plant, object facilities of the customer comprise a monitoring control LAN 22 , a monitoring unit 23 connected to this monitoring control LAN 22 , and a data collecting/transmitting unit 24 .
- a plurality of measuring instruments of the energy-saving equipment 26 are connected to the monitoring control LAN 22 via remote stations 25 , respectively.
- the monitoring unit 23 comprises a processing unit (CPU), a storage unit (HDD), and a display unit.
- the data collecting/transmitting unit 24 comprises a processing unit (CPU) and a storage unit (HDD).
- the monitoring unit 23 incorporates measured data such as temperature, heat and flow rate regarding energy consumption, in addition to quantities of energy such as consumed electric power, gas, oil and other fuel of the individual machines issued from the individual energy-saving facilities via the monitoring control LAN 22 and stores the data in the storage unit. In parallel with these measured data, data such as temperature, humidity and load such as production quantity exerting an effect on the energy consumption are incorporated as attribute data.
- the display unit of the monitoring unit can display the operating status, equipment maintenance information, energy-saving effect, operating costs (electricity, gas, oil, etc.), machine performance and failure, deterioration, and cost assessment from variable factors (electricity and gas).
- the management control system 31 on the energy service enterprise side comprises a remote information control server 32 , a corporate LAN 33 connected to this remote information control server 32 , and a printer 34 connected to this corporate LAN 33 .
- the remote information control server 32 is connected to the data collecting/transmitting unit 24 on the customer side via a communication transfer line 35 so as to permit communications.
- the communication transfer line 35 can operate by use of a public line or a mail as a medium.
- the remote information control server 32 comprises a processing unit (CPU), a storage unit (HDD) and a display unit.
- the display unit can display the same contents as those on the monitoring unit 23 on the customer side.
- the remote information control server 32 handles various duties relating to the aforementioned energy service business.
- FIG. 11 is a system configuration diagram of an embodiment of the co-generator.
- electric power is supplied to a load 43 by driving a generator 42 by means of a prime mover 41 such as a gas turbine.
- Cooling water is circulated by a pump 45 to the prime mover 41 via a waste heat recovering unit 44 so as to permit collection of heat by the prime mover 41 .
- the heat collected by the waste heat recovering unit 44 is fed to the load 47 by means of a heat medium circulated by a pump 46 .
- Waste gas discharge from the prime mover 1 is directed to a waste heat recovering boiler 48 , generates vapor by water fed from a pump 49 , and supplies the generated vapor to a load 50 .
- a flowmeter F, an entry thermometer T 1 , an exit thermometer, a wattmeter, and a temperature difference ⁇ T meter and other measuring instruments are arranged in each section to monitor the energy status.
- the output energy comprises power generation output and heat output and is determined by multiplying the generation output measured value E (kwH/h) by a heat conversion coefficient 860 (kcal).
- the heat output is determinable by multiplying the temperature difference between entry and exit (T 2 ⁇ T 1 ) of the waste heat recovering unit 44 and the waste heat recovering boiler 48 by the flow rate F and the specific heat of liquid (kcal/kg° C.).
- the efficiency of generating output and characteristic shown in FIG. 12 are periodically compared to determine whether or not appropriate.
- the characteristic curve shown in FIG. 11 is previously obtained through measurement and stored in the database. It is confirmed whether or not the energy-saving effect is retained as initially planned, by periodically comparing with a current value. An energy-saving effect over the planned value leads to a profit. If it is under the planned value, functions are restored by inspecting the facilities and equipment, and if malfunctions are found, conducting maintenance or repair.
- FIG. 13 is a system diagram of the refrigerator based on inverter driving.
- the refrigerator has a coolant cycle comprising the steps of condensing a coolant compressed by a compressor 51 in a condenser 52 , sending the condensed coolant to an evaporator 54 via an expansion valve 53 , and returning the coolant having released coldness back to the compressor 51 .
- Cold water cooling the condenser 52 is circulated to the coolant 56 via a pump 55 .
- Coolant is circulated to a space between the evaporator 54 and the cooling load by a pump 57 .
- a motor 58 driving the compressor 51 is driven at a variable speed by an inverter unit 59 .
- Ammeters A 1 and A 2 , voltmeters V 1 and V 2 , thermometers T 1 , T 2 , T 3 and T 4 and a flowmeter F are arranged to measure energy at various portions.
- the characteristic relationship between input energy (electricity input) and output energy (refrigerator output) of the refrigerator based on inverter driving having the above-mentioned configuration is as shown in FIG. 14 .
- a refrigerator using an inverter for motor driving and a refrigerator without inverter are shown in FIG. 14 .
- the energy saving effect by installing the energy-saving equipment such as co-generator and inverter driven refrigerator varies with the load of the energy-saving equipment, as shown in FIG. 12 or FIG. 14 .
- the energy consumption of the energy saving object facilities, such as the production facility increase with the load, such as the production quantity of the object facilities, for example, as shown by curve 61 in FIG. 15 .
- the energy consumption of the energy saving object facilities after taking the energy-saving measures is decreased, for example, as shown by curve 62 in FIG. 15 .
- the energy saving effect of the example of FIG. 15 corresponds to the hatched region, as shown, and increases with an increase in the production quantities of the production facility.
- the energy consumption of the energy saving object facilities vary with attribute data such as operating hours or operating rate, weather condition, (temperature, humidity), season, and day or night. Therefore, for calculation of the energy-saving effect comparison should be made of energy consumption with same condition of the attribute data before and after taking the energy-saving measures.
- the status of the other energy-saving facilities and equipments is monitored on the basis of the measured data thereof, and if the result is under the planned value, the machines are inspected. If a malfunction is found, recovery of functions is tried through maintenance or repair.
- the present invention is not limited to the above-mentioned form of contract, but any other form may be adopted. While a case where the energy service enterprise is responsible for payment of all the costs for energy-saving measures has been described above, the costs may be shared at certain ratios with the customer. The customer may bear all the costs. In these cases, the share of the energy service enterprise should naturally be approximately adjusted.
- the contract may take another form of assuring an energy-saving effect on the basis of the plan of energy-saving measures, and receiving payment of a certain amount of money from the customer in compensation for assessment.
- the energy service enterprise or a related organization drafts a plan of energy-saving measures, assures a quantity of energy curtailment, under certain conditions, available when installing energy-saving facilities in accordance with the planned measures, measures the energy consumption after taking the energy-saving measures, determines the difference of the measured value from the energy consumption before taking the energy-saving measures previously stored in the database, and confirms the assured quantity of curtailment periodically.
- the energy service enterprise can receive compensation in a fixed amount or at a fixed rate in response to the amount of curtailed energy cost as a reward for successful achievement. When contributing investment funds, this enables the customer to introduce energy-saving facilities with confidence.
- the certain conditions for assurance cover factors which may exert an important influence on the curtailment effect of the energy consumption such as the operating rate or operating hours of the facilities to which the energy-saving measures are applied energy-saving object facilities, and the operating conditions of the energy-saving object facilities (production quantity, batch processing frequency, etc.).
- the certain conditions may have ranges.
- Weather conditions temperature, humidity
- which exert an important effect on the energy-saving effect can be coped with by using past data under the same conditions.
- the energy service enterprise When the quantity of energy curtailment is under the assured value, the energy service enterprise performs maintenance of the energy-saving facilities so as to satisfy the assured value, or improves the energy-saving facilities.
- the contract should set forth that the energy service enterprise receives a compensation in response to the quantity of energy curtailment in excess of the assured value.
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- Educational Administration (AREA)
- General Physics & Mathematics (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Development Economics (AREA)
- Health & Medical Sciences (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Power Engineering (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
An energy service business system includes a database which stores past data about an energy consumption of a facility before taking energy-saving measures, a measurer which measures present data of the energy consumption after taking the energy-saving measures, and a calculator which calculates energy curtailment quantities facility before and after taking the energy-saving measures. The past data in the database are stored in a form correlated with data of a production quantity, and the measurer measures the present data of the energy consumption together with data of the production quantity after taking the energy-saving measures. The calculator retrieves the past data having production quantity data within a set allowable range corresponding to the measured present data having production quantity data, and calculates the energy curtailment quantities by comparing the retrieved past data having production quantity data and the measured present data having the production quantity data.
Description
- This application is a continuation-in-part of U.S. application Ser. No. 09/843,736, filed Apr. 30, 2001, the contents of which are incorporated herein by reference.
- 1. Field of the Invention
- The present invention relates to energy service business method and system.
- 2. Description of the Related Art
- There is an increasing interest in the world in global warming and environmental preservation, and efforts for improvement are internationally made. For example, it is demanded to take energy-saving measures to business enterprises of plants and buildings, major energy consumers, to determine energy-saving target values, and achieve such target values within a certain period of time.
- Research and development efforts of energy-saving techniques are made in various fields under these circumstances, including, for example, research and development of energy-saving equipment and facilities for curtailing the energy consumption, and energy-saving measures based on specific operating method or controlling method of energy-saving object facilities. In this specification, all these energy-saving equipments, energy-saving facilities, energy-saving operation and control will be called generically energy-saving facilities or measures.
- In general, business enterprises demand to collect the investment cost for taking energy-saving measures by means of an energy cost capable of being curtailed through energy conservation. In addition, if the investment cost can be collected within the shortest possible period of time, it would largely promote energy-saving measures.
- However, while a reference of about three years is generally believed to be desirable for collection of invested funds to be examined when an enterprise makes an equipment investment, achievement of a high energy conservation target value would require five to six years for collecting the invested funds. If the amount of curtailment of energy costs through energy conservation is smaller than initially expected, furthermore, investment collection would require more years, resulting in a problem of difficulty to adopt measures for achieving a high energy-saving target value.
- Accordingly, it is an object of the present invention to make it easier to apply energy-saving measures.
- To solve the above-mentioned problems, the invention permits easier introduction of energy-saving measures by creating the following energy service businesses.
- A first form of management is characterized in that the investment cost for energy-saving measure is derived from contribution of funds by energy service enterprises and energy conservation effect, i.e., curtailment of the energy costs. More specifically, the process comprises the steps of applying energy-saving measures to object facilities at the cost of an energy service enterprise, measuring the energy consumption after taking energy-saving measures, and calculating the amount of curtailment of the energy costs by comparing the thus measured value with the energy consumption before taking the energy-saving measures previously stored in a database, and allowing the energy service enterprise to receive at least a part of the amount of curtailment. According to this form of management, the customer, not required to make an equipment investment for taking energy-saving measures and plan collection thereof, is easier to introduce energy-saving measures. As a result, introduction of energy-saving measures is encouraged, and inhibition of global warming and preservation of environments are promoted.
- In this case, it is desirable to store the energy consumption before taking energy-saving measures, together with attribute data of variable factors of the energy consumption, in the database, measuring the energy consumption after taking the energy-saving measures, together with the attribute data, and compare the measured value with the energy consumption before taking the energy-saving measures corresponding to the measured attribute data. The attribute data is characterized by being at least one of temperature, humidity and load quantity of the object equipment. It is desirable to retrieve a plurality of past data corresponding to a plurality of attribute data approximating the measured attribute data, perform calculation for estimating past data corresponding to the measured attribute data from the plurality of past data, and compare the measured data with the calculated past estimated data.
- The amount received by the energy service enterprise should preferably be determined with reference to the operating hours or the operating rate of the object equipment. When the quantity of energy curtailment is under a predetermined reference value, the energy service enterprise provides maintenance or improvement without compensation of the equipment to which the energy saving is applied so as to satisfy the reference value.
- More specifically, the amount received by the energy service enterprise is, when the total amount of the fixed costs such as depreciation and tax and tariffs for a single fiscal year for taking energy-saving measures and the variable costs such as maintenance cost of energy-saving equipment is Q, the annual amount of curtailment of energy costs is P, and α and β are positive coefficients (where α>β):
- X1% of curtailment amount of energy cost when P≧αQ;
- X2% of curtailment amount of energy costs when 62 Q.≦P<αQ (where, X1<X2); and
- a predetermined amount when P<βQ.
- X2 is calculable by the following formula:
X2=X1+(α−P/Q)(100−X1)/(α−β). - In this case, the amount collected by the energy service enterprise is determinable on the basis of the operating hours or the operating rate of the energy-saving object equipment or the energy-saving equipment. The energy service enterprise can receive an amount of collection in response to an amount of energy cost curtailment calculated periodically (every three months, for example).
- When the quantity of energy curtailment is smaller than an assured value, the energy service enterprise performs maintenance of the energy-saving equipment or improvement thereof so as to satisfy the assured value.
- The customer and the energy service enterprise may share the installation cost of the energy-saving equipment to install the same. In this case, the energy service enterprise receives an amount calculated by distributing the amount of energy cost curtailment in accordance with the share thereof.
- A second form of management of the invention is characterized in that the energy service enterprise drafts a plan and executes energy-saving measures and assures an energy-saving effect, i.e., an amount of energy cost curtailment, irrespective of whether or not the energy service enterprise contributes investment funds for the energy-saving measures. More specifically, this process comprises the steps of drafting energy-saving measures by the energy service enterprise or a related organization thereof; assuring, under certain conditions, a quantity of curtailment of energy consumption available when taking energy-saving measures in accordance with the thus drafted measures; measuring the energy consumption after taking the energy-saving measures; calculating the amount of curtailment of energy costs by comparing the thus measured value with the energy consumption before taking the energy-saving measures previously stored in a database, and periodically confirming the assured quantity of curtailment.
- This enables a general business enterprise to introduce energy-saving facilities free from care. The certain conditions are conditions determined as to variable factors having an important effect on curtailment of the energy consumption such as the operating rate or operating hours, operating conditions (production quantity, frequency of batch processing, etc.) of the energy-saving object equipment. The certain conditions can have ranges. Weather conditions (temperature, humidity) which have an important effect on the energy-saving, can be coped with by using past data obtained under the same conditions. If past data under the same conditions are unavailable, approximate data are used through interpolation or extrapolation.
- When the quantity of curtailment is under the assured value, the energy service enterprise should preferably perform maintenance of the energy-saving equipment or improvement thereof so as to satisfy the assured value. In this case, it is desirable that the energy service enterprise can receive a compensation in an amount corresponding to the quantity of energy curtailment in excess of the assured value in reward for assuring a quantity of energy curtailment, or as a cost to be appropriated for maintenance and improvement.
- The method of business as described above can be achieved by adopting a system comprising a database which stores past data about the energy consumption before taking energy-saving measures; measuring means which measures the energy consumption after taking energy-saving measures; and calculating means which calculates the energy curtailment quantities before and after taking energy- saving measures by incorporating measurement data measured by the measuring means via a communication line and comparing the measurement data and the past data stored in the database.
- In this case the past data in the database are stored together with attribute data regarding variable factors of the energy consumption. The attribute data represents at least one of temperature, humidity and load quantity of an energy-saving object equipment.
- The calculating means calculates the amount of curtailment of the energy costs on the basis of the energy curtailment quantity, and issues a bill demanding payment of an amount obtained by multiplying the amount of curtailment by a predetermined ratio.
- Other objects and advantages of the present invention will become apparent from the following description made with reference to the attached drawings.
-
FIG. 1 illustrates a flowchart of energy-saving measures of an embodiment of the energy service business method of the present invention; -
FIG. 2 is a conceptual view illustrating a form of contract of the energy service business method of the invention; -
FIG. 3 illustrates the concept of allocation of profit under the energy-saving effect in the energy service business method of the invention; -
FIG. 4 is a descriptive view of an example explaining energy-saving object facilities and an energy-saving equipment; -
FIG. 5 is a flowchart illustrating a detailed procedure for evaluation of the flow shown inFIG. 1 and setting of years under contract; -
FIG. 6 is a diagram explaining the relationship between the annual operating hours and annual expenses/accrued costs of an energy-saving equipment; -
FIG. 7 is a flowchart illustrating the calculating procedure of the annual profit of the flow shown inFIG. 1 and expenses of the energy service enterprise; -
FIG. 8 is a flowchart illustrating contents and procedure of management control of the energy-saving equipment in the flow shown inFIG. 1 ; -
FIG. 9 illustrates (A) and (B), two examples of determination of the sharing ratio of the energy-saving effects; -
FIG. 10 is a configuration diagram illustrating an embodiment of the management control system of the energy service business method; -
FIG. 11 is a system configuration diagram of an embodiment of a co-generator; -
FIG. 12 illustrates generating output and efficiency properties of a co-generator; -
FIG. 13 is a system diagram of a refrigerator based on inverter driving; and -
FIG. 14 is a diagram illustrating the relationship between input energy (electric input) and output energy (refrigerator output) of an inverter-driven refrigerator and a refrigerator without inverter; -
FIG. 15 is a diagram showing a relationship of energy consumption and production quantity. - Embodiments of the energy service business including a method of management of an energy service business of the present invention will now be described.
FIG. 1 illustrates an embodiment of flowchart of the energy-saving measures in an energy service business method. - (Step S11)
- The work of energy-saving measures begins with, upon customer's request, investigation of the current status of energy-saving object facilities and diagnosis as to energy conservation. Energy-saving object facilities include, all types of equipment, facilities, machines, and apparatuses consuming energy such as various production facilities, utility facilities (such as electric power, gas, heat, air and water), general buildings (such as office buildings, hospitals and public facilities). Energies consumed, in addition to electric power, gases, and heat (cold and warm), include utilities such as water, air and the like.
- Investigation of the current status of energy-saving object facilities (hereinafter simply referred to as “object facilities”) covers timing of introduction of object facilities, status of facilities such as operating hours or number of days, and energy consumption.
- (Step S12)
- Then, a plan of energy-saving measures is drafted. First, a basic plan of energy-saving measures by setting basic conditions for the installation space for the energy-saving facilities, amount of investment, electric power under contract, number of years of depreciation, impact on environments, and future expansion plan. Electric power under contract is set because the power unit price varies with the electric power under contract. The energy-saving measures include replacement of existing facilities by energy-saving type new facilities, addition of energy-saving facilities, proposal of maintenance for energy conservation, and proposal of management and control of facilities for energy saving.
- (Step S13)
- Then, for a draft modification plan, the operating cost, equipment cost, maintenance expenses and personnel cost are tentatively calculated. Simultaneously, the curtailment effect of CO2 by energy saving is tentatively calculated to approximately evaluate validity of the modification plan. That is, the increase in various costs required for introduction of energy-saving facilities and the cost curtailment effect of energy conservation are macroscopically and comparatively examined, and the validity of the basic modification plan is assessed regarding the presence of troubles caused by introduction of the energy-saving facilities.
- (Step S14)
- When the plan is assessed not to be valid, the plan is discontinued, and when it is assessed to be valid, the following detailed planning is conducted.
- (Step S15)
- In this step, the current energy consumptions are measured for the object facilities, and detailed energy diagnosis is performed. This diagnosis gives past data used when calculating the energy-saving effect, as described later. The energy consumptions of the object facilities vary with the load such as the production quantity of the object facilities, operating hours or operating rate, weather conditions (temperature, humidity), season, and day or night. Therefore, in order to calculate the energy-saving effect by comparing energy consumptions before and after modification, it is necessary to collect energy consumption data for the individual object facilities before modification to be compared, together with attribute data such as load on the object facilities, temperature and humidity, for the longest possible period of time, and prepare a database of past data before modification.
- (Step S16)
- A concrete energy-saving measures are planned on the basis of the database prepared in step S15. A method of energy-saving measures comprises the steps, for example, of investigating the pattern of daily power consumption or heat energy consumption for the object equipment, and when the daytime power consumption is very small as compared with the night one, storing electric energy in the night in an ice heat accumulating system, an accumulator, or a power storage equipment, releasing the same in the daytime, and balancing the power between day and time, thereby curtailing the power cost. It is necessary to examine introduction of energy-saving facilities generating electric power and heat by burning a fuel such as oil or gas such as a composite generator (co-generator). Furthermore, the driving motor of a pump or a fan is converted into inverter control, and energy conservation is achieved by controlling the number of revolutions of the motor in response to a load thereof. Various often energy-saving measures are proposed.
- After thus planning concrete energy-saving measures, the curtailment effort of the energy consumption is tentatively calculated for the care when these energy-saving measures are taken. In this case, the effect thereof on environments is taken into account, and at the same time, labor saving and achievement of a higher efficiency are accomplished for the control of the energy facilities.
- (Step S17)
- As a result of examination of modification plan, evaluation is conducted as to whether of not the available energy-saving effect is sufficient to permit collection of the investment cost required for modification of facilities. Details of this evaluation will be described later. In summary, the evaluation criterion is whether or not the investment funds for the energy-saving measures can be collected within an appropriate number of years (for example, within ten years at the latest). When an evaluation that the amount of investment can be collected within an appropriate number of years is obtained, the customer and the energy service enterprise consider entering into a contract specifying that number of years as the years under contract and the customer shall pay a part of the curtailed amount of energy cost under the energy-saving effect to the energy service enterprise.
- In this embodiment, a contract form as shown in the conceptual view illustrated in
FIG. 2 is adopted. As shown inFIG. 2 , the investment cost required for energy-saving measures applied to the energy-saving object facilities of the customer I, i.e., the modification cost including the installation cost of the energy-saving-equipment is borne by the energy service enterprise II. The energy service enterprise III is financed by a financial institution III with investment funds as required. The energy-saving enterprise III enters with the customer I into a contract for sharing the amount of curtailed energy cost achieved under the energy-saving effect a certain ratio with the customer. A concrete example of the distribution contract will be described later. As shown in the conceptual view ofFIG. 3 , the customer I and the energy service enterprise II share the amount of curtailment of the energy cost after taking the measures from the energy cost before taking the measures. The energy service enterprise thus carries out business with the dividend paid by the customer as income. More particularly, the energy service enterprise carries out business by appropriating the dividend income for repayment of the loan financed by the financial institution III, and on the other hand, for management and control (verification, maintenance and improvement) of the energy-saving facilities. The distribution ratio of dividend may be determined on the basis of the operating hours or operating rate of the energy-saving facilities. Since the energy-saving effect largely varies with the operating rate among others, the contract should preferably set forth that the distribution ratio for the energy service enterprise II shall be reduced when the operating rate is high. A concrete example of distribution will be described later. - (Step S18)
- When the both parties agree upon the contractual terms and conditions, a contract for implementation and management of energy-saving measures in entered into.
- (Step S19)
- The energy service enterprise or a related organization thereof conducts a detailed design of the energy-saving measures under the contract, and executes the work including installation of energy-saving equipments and modification of existing facilities.
- (Step S20)
- After implementation of the energy-saving measures, the energy service enterprise carries out management and control of services for the energy-saving measures including surveillance of the energy-saving equipment, verification of the energy-saving effects, maintenance and improvement. More specifically, the energy consumption after taking energy-saving measures, and voltage, current, flow rate of fuel, flow rate of a fluid such as coolant and temperature necessary for calculating the energy consumption are periodically (for example, every 15 minutes or every hour) measured, and recorded as measured data. Attribute data such as load on the object facilities, temperature and humidity are measured in parallel with this, and recorded together with the measured data including the energy consumption. The quantity of energy curtailment is calculated by comparing the same or substantially the same measured with past data previously stored in the database. If there is not found the same substantially the same data, approximation is performed through interpolation or extrapolation. The amount of curtailed energy cost is calculated on the basis of the thus calculated quantity of curtailed energy and the energy unit price set forth in the contract. Dividend is calculated periodically (for example, monthly, every three to 12 months), on the basis of this amount of curtailment. The energy-saving effect is reported to the customer, and payment of the dividend is demanded.
- When the quantity of energy curtailment is under a predetermined reference value of an assured value, on the contrary, the energy service enterprise provides maintenance or improvement of the energy-saving equipment without compensation so as to satisfy the reference value. Control is performed so as to satisfy the assured value or the reference value of the quantity of curtailed energy by appropriately monitoring the data recorded through measurement of the energy consumption after taking the energy-saving measures, determining whether or not the energy-saving equipment displays, determining performance, and applying maintenance or the like as required.
- Main portions in the flowchart of
FIG. 1 will now described in detail.FIG. 4 illustrates a concrete example of energy-saving measures to be examined in step S12 or S16 shownFIG. 1 . The object facilities shown inFIG. 4 represent the case of research institute. In view of the basic fact that energy consumption is considerably smaller than that in daytime, the following energy-saving measures are examined. - a. Electric power storage facilities 1:
- Power charges are reduced by storing night electric power of a lower rate, and releasing the same at the daytime peak of power consumption, thus leveling the power consumptions. In general, reducing the contract power reduces the power unit price.
- b. Ice heat accumulating system 2:
- This serves as a cooling source of air conditioning and other facilities. Power charges can be reduced by manufacturing ice by use of night electric power, and utilizing the low temperature of ice for air conditioning during daytime, thus reducing the daytime power consumption through leveling of the power consumptions.
- c. Solar generation facilities 3:
- The power consumption can be leveled between night and daytime by generating power from sun light during the daytime.
- d. Composite generating system (Co-generator) 4:
- Power consumptions are leveled between night and daytime by generating power through driving of a prime mover such as an engine by a gas or oil fuel, and on the other hand, waste heat of prime mover is used for air conditioning and hot water supply. Particularly, use of a dispersion type composite generating system permits improvement of energy efficiency and reduction of driving noise.
- e. Cooling source (cooling tower) 5:
- The capacity of pumps for cooling water and cold water can be reduced and the power consumption is curtailed by improving the cooling efficiency of the cooling tower and increasing the temperature difference between entry and exit of cooling water and cold water.
- f. Motor inverter control 6:
- Power saving can be achieved by changing control of driving motors for air conditioner fans and cold water pumps into inverter control, and reducing the number of revolutions in response to the air conditioning load.
- g. Power receiving and transforming equipment 7:
- Power consumption can be reduced by reducing loss (no-load loss, load loss) of the power receiving and transforming machines such as transformers.
- h. Energy-saving illuminating appliances 8:
- Power consumption is saved by operating fluorescent lumps with a high-frequency inverter. Contrivances are made in lighting so as to use sunlight during daytime. Illuminance is improved by pasting a high-reflectivity film to the reflector.
- i. Management control of energy conservation 9:
- The operating status of the facilities and the energy consumption is monitored, and improvement is examined for facilities showing water of energy or a poor efficiency, if any.
- j. Other measures:
- Processed water discharged from a
water treatment equipment 10 is reused as so-called intermediate water, thereby effectively utilizing water resources. Efforts are made also to reduce the quantity of dust and waste. - The procedure for assessing a plan and setting a number of years under contract in step 17 shown in
FIG. 1 will now be described with reference to FIGS. 5 to 7. - (Step S21 and S22)
- The initial value n of contract years is set (S21), and various costs for evaluating the energy-saving are calculated (S21). More particularly, the investment cost for energy-saving measures is collected with a number of years n under contract. For example, the depreciation cost and the fixed costs comprising tax and tariffs such as fixed asset tax, insurance premium and other general expenses and tentatively calculated for each fiscal year (single fiscal, year). The variable costs comprising maintenance cost necessary for maintaining the performance of the energy-saving equipment are also tentatively calculated. On the other hand, the amounts of curtailed energy cost K=aH before and after taking the energy-saving measures are tentatively calculated for the energy-saving object facilities. The amount of curtailment is calculable by multiplying the quantities of curtailed energy before and after taking the energy-saving measure by an energy unit price: a represents an amount of curtailed energy cost per unit operating time (curtailment coefficient); and H, annual operating hours of the object equipment. The mount of curtailment K increases according as the annual operating hours of the energy-saving equipment H is longer. The relationship between the annual cost/accrued costs and the annual operating hours is as shown in
FIG. 6 . - (Step S23)
- When the energy service enterprise contributes the investment cost for the energy-saving measures, and holds the equipments installed or modified for such measures, the depreciation cost (1) and expenses including tax and tariffs (2) would borne by the energy service enterprise. The maintenance cost (3) for assuming the energy-saving effect is also at the cost of the energy service enterprise. Accordingly, in step S23, the amount of curtailed energy (energy-saving effect) P available from the energy-saving measures and the annual total expense Q for the energy service enterprise an tentatively calculated in accordance with the following formula:
P=Amount of curtailed energy K
Q=Depreciation (1)+expenses (2)+maintenance (3) - (Step S24)
- If the energy-saving effect P surpasses the annual total expense Q, which means that the energy-saving measures pay, P=Q would be the break-even-point. In order to obtain a profit as a business, P>Q is preferable, and the number of contract years necessary for collection of investment funds is required to be up to ten years, or preferably five to six years. Because the amount of energy curtailment increases with the annual operating hours H, the number of contract years n can be reduced according as the annual operating hours H increase. The appropriateness of the number of contract years n is therefore determined using as a standard the annual number of operating hours B when P=1.1Q.
- (Step S25)
- It is determined whether of not the ratio of P to Q determined in Step S23 satisfies the range of the following formula:
1.08<P/Q<1.15
If this formula is not satisfied, the process advances to step S26. - (Step S26 and S27)
- If P/Q is under the above-mentioned range, the contract number of years n is extended for another one year (S26), and returning to step S22 via step S27, and the aforementioned processing is executed again. When repetition leads to the number of contract years of over ten years, the examination is discontinued (step S27).
- (Step S28)
- If P/Q is within the above-mentioned range in the determination in step S25 as a result of repetition of processing, the number of contract years N is determined in step S28.
- The details of steps S22 and S23 will now be described with reference to the flow shown in
FIG. 7 . - (Step S31)
- The depreciation cost (1) for each fiscal year is calculated on the assumption that the costs for the energy-saving measures are to be depreciated in the number of contract years. Necessary data in this calculation include the personnel cost, materials cost, processing cost and the increment ratios thereof, which are on stored in the database.
- (Step S32)
- Calculation of the tax and tariff expenses (2) such as fixed asset tax in executed. Data necessary for this calculation include fixed asset tax, and excise, which are stored in the database.
- (Step S33)
- Time t from among the calculation parameters is reset to t=0.
- (Step S34)
- The maintenance cost (3) is calculated in step S34. That is, costs required for maintenance, inspection and modification necessary for assuring or keeping the energy-saving effect. Data necessary for this calculation include personnel cost, materials cost, processing cost and increment ratios thereof, which are stored in the database.
- (Step S35)
- The energy consumption for the object facilities and the energy consumption for management of the energy-saving equipment. Data necessary for this calculation include:
- (1) Weather conditions (temperature, humidity);
- (2) Load (plant, general building, etc.) operation or operating conditions (for example, production quantity, batch processing frequency, etc.);
- (3) Past operating data of facilities and equipments (for example, data in the form of energy characteristics curves of partial load, as derived from operating data for a past few years);
- (4) Characteristics data of facilities and equipments (motor efficiency curve, machine performance curve, characteristics of rotary machines such as refrigerator, pump, fan and compressor, characteristics of prime mover, etc.);
- (5) Operating data (annual operating days, daily operating hours).
- (Step S36)
- The amount of curtailment which represents the energy-saving effect after taking the energy-saving measures is calculated on the basis of the energy consumptions calculated in step S35. The amount of curtailment in this case can be calculated in units of a month, or three to 12 months. Data necessary for this calculation include charge data of electricity, gas, oil and water and tax data such as excise, which are stored in the database.
- (Step S37 and S38)
- In step S37, it is determined whether or not the energy-saving effects of step S36 have been added up for a full year. If not, one hour is added to t in step S38, and returning to step S34, the process is repeated.
- (Step S39)
- Depending upon the determination made in step S37, the annual project (energy-saving effect) p and the expenses Q for the energy service enterprise are calculated on the basis of the amounts of curtailed energy K before and after taking the energy-saving measures, and the process domes to an end.
-
FIG. 8 illustrates contents and procedure of management control after startup of operation of the energy-saving equipment upon the completion of detailed design and modification work of the energy-saving measures under the contract (S18) entered into upon agreement between the customer and the energy service enterprise, as represented in the concrete flow of step S20 shown inFIG. 1 . - (Step S41)
- In the flow of
FIG. 8 , the process is executed at intervals of a certain period of time (Δt: for example, every 15 minutes or every hour): preparation and submission of a report to the customer as an end, the time counter t is reset to 0, and repetition is started. - (Step S42)
- Energy-saving calculation is executed for each machine. A remote information control server executing the process of
FIG. 8 is provided, for example, on the energy service provide side. Therefore, measured data necessary for calculating the energy conservation for each machine are measured via a monitor provided on the energy-saving object facilities and the energy-saving equipments, collected by a data collecting and transmitting unit, and transferred to the remote information control server. - The measured data include, in addition to quantities of energy consumed electric power and fuel quantities such as gas and oil for each equipment, physical quantities such as temperature, heat and flow rate regarding the energy consumption. Machines include a motor, a pump, a fan, an air compressor, a compressive refrigerator, a suction type refrigerator, and a co-generator (composite generator) and other prime movers.
- Together with the measured data, load data having an effect on the energy consumption such a temperature, humidity and production quantity are measured as attribute data and collected and transferred. The measured data including the thus transferred attribute data are once stored, for example, in a working memory of the remote information control server of a database. Energy consumptions of the individual machines are calculated on the basis of the measured data thus stored in the database.
- (Step S43)
- For the energy consumption or the measured data for the individual machines calculated in step S42, the past energy consumptions or past data of the corresponding machine are retrieved from the database, and the energy-saving effect, i.e., the quantity of energy curtailment is tentatively calculated by comparing these data.
- (Step S44)
- Data are compared so as to see whether or not the energy-saving effect calculated in step S43 reaches the quantity of initially planned effect. If the planned value is not reached by the energy-saving effect, the process proceeds to steps S45 and S46, and when it is reached, the process goes to step S47.
- (Steps S45 and S46)
- When the energy-saving effect does not reach the planned value, details of malfunction of the machine is estimated on the basis of the measured data, and a check instruction of the corresponding malfunctioning machine is issued, returning to step S47.
- (Step S47)
- In this step, it is determined for all the machines whether or not the energy-saving effect has been calculated. If not, the process returns to step S42, and the process of tentatively calculating the energy-saving effect for each machine is repeated. Upon the completion of tentative calculation of the energy-saving effect for all the machines, the process advances to step S48.
- (Step S48)
- The quantities of energy saving, i.e., the energy-saving effects for all the machines are added up in this step S48 to calculate the quantity of energy curtailment resulting from the energy-saving measures.
- (Step S49)
- In this step, the planned value of the quantity of energy curtailment agreed upon between the energy service enterprise and the customer is compared for evaluation with the quantity of energy curtailment calculated in step S48.
- (Steps S50, S51 and S52)
- If the initially planned value is not satisfied, the reason of non-satisfaction is retrieved in step S51. For example, examination is made by, for example, comparing characteristics of the corresponding machines with the initially planned characteristics. If it is satisfied, n the other hand, the process proceeds to step S52, and the time counter is put forward by Δt.
- (Step S53)
- In this step, it is determined whether or not it is a report timing to the customer as set forth in the contract (for example, a month, three months, six months and a year). If not the report timing, the calculated result is stored as result data in the database, returning to step S42 to repeat the process. It is a report timing, the process advances to step S55.
- (Step S55)
- First, a bill is prepared on the basis of the result of tentative calculation of the energy-saving effect. As described above, a amount based on a ratio corresponding to the energy-saving effect as get forth under the contract is demanded. An example of determination of this amount will be described on the assumption that the energy service enterprise is responsible for payment of the costs necessary for the energy-saving measures. As described above with reference
FIG. 6 , if the total amount of the fixed costs such as the depreciation (1) for a single fiscal year for the energy-saving measure and the tax and tariffs (2) and the variable costs (3) including the maintenance cost of the energy-saving equipment is Q; the annual amount of curtailed energy cost is P(=K), and α and β are position coefficients (where, α>β), the contract sets forth that the energy service enterprise receives: - X1% of the amount of curtailed energy cost when P≧αQ;
- X27% of the amount of curtailed energy cost when βQ≦P≦αQ (where X1<X2); and
- a predetermined amount when P<βQ.
-
FIG. 9 (A) illustrates example of shares. A case where α=1.1 and β=1.03 are set will be described. A case where the annual operating rate or operating time is near the break-even-point (P=Q) is represented by α=1.1. Setting a reference value or a planned value of the annual operating rate at such a point leads to an increase in the number of contract years, i.e., the number of years required for collecting the costs. This is therefore unrealistic. In the case of an annual operating rate lower than α=1.1, on the other hand, the absolute value of the amount of curtailed energy is also smaller. When distributing an amount of curtailed energy cost (annual profit), therefore, an amount over a certain amount of curtailment should be set as a planned value. When P≧1.1Q, for example, a contract should preferably be entered into by setting forth a share of the energy service enterprise of X=95% and a share of the customer of Y=5%. The share of the energy service enterprise is larger because the enterprise is responsible for paying all the costs for the energy-saving measures, and this forms one of the features of the method of the present invention. - When the annual operating time is smaller than the planned value, which is often caused by circumstances on the customer side, the share of the energy service enterprise should preferably be increased from the point of view of collecting the investment funds. Since a smaller number of annual operating hours exerts a more serious effect such as dispersion of measured data, β=1.03 should be set forth, and in a case with a smaller β, the share of the energy service enterprise is increased to 100%. Within the range of 1.03Q≦1.1Q, therefore, the share of the energy service enterprise of X2% is gradually increased from 95% to 100% as is suggested by the following formula:
In a case with P<1.03Q, the energy service enterprise receives payment of a certain amount as a minimum guarantee for the necessity to collect the invested funds. This amount should preferably be an amount corresponding to the total of the depreciation (1), the expenses (2) and the maintenance cost (3) as shown inFIG. 6 , but it depends upon agreement between the parties. -
FIG. 9 (B) shows another example of distribution. In the example shown, with reference to an assessed amount or an expected amount under contract, if the energy-saving effect is over this value, the share of the energy service enterprise is increased to X3, as compared with the share of X when the effect is equal to the expected value, to serve as a bonus. When the effect is under the contract value, the share of the enterprise may be decreased even to X4 in some cases. When the energy service enterprise has intention to repay an amount Z to the financial institution on the basis of the share X, and the share is increased to X3, the energy service enterprise puts the increment of share Z3 aside provisionally, and when the share becomes X4, on the contrary, manages the business so as to provisionally loan the decrement of share Z4. - (Step S56)
- The energy service enterprise prepares a result report of energy conservation and submits the same to the customer together with a bill, the process returning to step S41 to repeat the steps.
-
FIG. 10 illustrates an embodiment of the management control system of the aforementioned energy service business method. As shown inFIG. 10 , the management control system provided in a building or a plant, object facilities of the customer comprise amonitoring control LAN 22, amonitoring unit 23 connected to thismonitoring control LAN 22, and a data collecting/transmittingunit 24. A plurality of measuring instruments of the energy-savingequipment 26 are connected to themonitoring control LAN 22 viaremote stations 25, respectively. Themonitoring unit 23 comprises a processing unit (CPU), a storage unit (HDD), and a display unit. The data collecting/transmittingunit 24 comprises a processing unit (CPU) and a storage unit (HDD). - In the management control system on the customer side having the above-mentioned configuration, the
monitoring unit 23 incorporates measured data such as temperature, heat and flow rate regarding energy consumption, in addition to quantities of energy such as consumed electric power, gas, oil and other fuel of the individual machines issued from the individual energy-saving facilities via themonitoring control LAN 22 and stores the data in the storage unit. In parallel with these measured data, data such as temperature, humidity and load such as production quantity exerting an effect on the energy consumption are incorporated as attribute data. The display unit of the monitoring unit can display the operating status, equipment maintenance information, energy-saving effect, operating costs (electricity, gas, oil, etc.), machine performance and failure, deterioration, and cost assessment from variable factors (electricity and gas). - The
management control system 31 on the energy service enterprise side comprises a remoteinformation control server 32, acorporate LAN 33 connected to this remoteinformation control server 32, and aprinter 34 connected to thiscorporate LAN 33. The remoteinformation control server 32 is connected to the data collecting/transmittingunit 24 on the customer side via acommunication transfer line 35 so as to permit communications. Thecommunication transfer line 35 can operate by use of a public line or a mail as a medium. The remoteinformation control server 32 comprises a processing unit (CPU), a storage unit (HDD) and a display unit. The display unit can display the same contents as those on themonitoring unit 23 on the customer side. The remoteinformation control server 32 handles various duties relating to the aforementioned energy service business. For example, calculation of merits depending upon the operating status (energy-saving effect), distribution of operational merits based on the contract, preparation of a bill on the basis of the operational merits, changing conditions for tentative calculation of operational merits upon occurrence of a variable factors, and the like. The bill is sent to the customer via mail, attached with operating status data. - Because of the aforementioned configurations, only necessary data predetermined by the data collecting/transmitting
unit 24 from among measured data and attribute data such as temperature and humidity, collected by themonitoring unit 23 and stored in the storage unit are read out and transferred to, and stored in, a database or a working memory composing the storage unit of the remoteinformation control server 32 via thecommunication transfer line 35. These measured data are transferred periodically (for example, every 15 minutes). - A concrete embodiment of the energy-saving equipment will now be described with reference to FIGS. 11 to 14.
FIG. 11 is a system configuration diagram of an embodiment of the co-generator. As shown inFIG. 11 , electric power is supplied to aload 43 by driving agenerator 42 by means of aprime mover 41 such as a gas turbine. Cooling water is circulated by apump 45 to theprime mover 41 via a wasteheat recovering unit 44 so as to permit collection of heat by theprime mover 41. The heat collected by the wasteheat recovering unit 44 is fed to theload 47 by means of a heat medium circulated by apump 46. Waste gas discharge from theprime mover 1 is directed to a wasteheat recovering boiler 48, generates vapor by water fed from apump 49, and supplies the generated vapor to aload 50. A flowmeter F, an entry thermometer T1, an exit thermometer, a wattmeter, and a temperature difference ΔT meter and other measuring instruments are arranged in each section to monitor the energy status. - Efficiency monitoring of the co-generator having the above-mentioned configuration will now be described. First, input energy takes a value equal to the product of multiplication of the generated heat of the fuel fed to the
primer mover 1 HV (kcal/1 or kcal/m3) and the measured flow rate Ff (1/h or m3/h). On the other hand, the output energy comprises power generation output and heat output and is determined by multiplying the generation output measured value E (kwH/h) by a heat conversion coefficient 860 (kcal). The heat output is determinable by multiplying the temperature difference between entry and exit (T2−T1) of the wasteheat recovering unit 44 and the wasteheat recovering boiler 48 by the flow rate F and the specific heat of liquid (kcal/kg° C.). The generation efficiency ηE, and the heat recovery efficiency ηH are determined by the following formula, where i is 1 or 2, corresponding to the wasteheat recovering unit 44 and the waste heat recovering boiler 48:
ηE=E×860/HV·Ff
ηH=Σ(Fi×(T2·T1)×Ci)/HV·Ff - For the thus determined generating efficiency ηE and heat recovery efficiency ηH, the efficiency of generating output and characteristic shown in
FIG. 12 are periodically compared to determine whether or not appropriate. The characteristic curve shown inFIG. 11 is previously obtained through measurement and stored in the database. It is confirmed whether or not the energy-saving effect is retained as initially planned, by periodically comparing with a current value. An energy-saving effect over the planned value leads to a profit. If it is under the planned value, functions are restored by inspecting the facilities and equipment, and if malfunctions are found, conducting maintenance or repair. -
FIG. 13 is a system diagram of the refrigerator based on inverter driving. The refrigerator has a coolant cycle comprising the steps of condensing a coolant compressed by acompressor 51 in acondenser 52, sending the condensed coolant to anevaporator 54 via anexpansion valve 53, and returning the coolant having released coldness back to thecompressor 51. Cold water cooling thecondenser 52 is circulated to thecoolant 56 via apump 55. Coolant is circulated to a space between the evaporator 54 and the cooling load by apump 57. On the other hand, amotor 58 driving thecompressor 51 is driven at a variable speed by aninverter unit 59. Ammeters A1 and A2, voltmeters V1 and V2, thermometers T1, T2, T3 and T4 and a flowmeter F are arranged to measure energy at various portions. - The characteristic relationship between input energy (electricity input) and output energy (refrigerator output) of the refrigerator based on inverter driving having the above-mentioned configuration is as shown in
FIG. 14 . A refrigerator using an inverter for motor driving and a refrigerator without inverter are shown inFIG. 14 . These data are previously measured and stored in a database or the like. The input energies include inverter-input energy E1 and motor-input energy E2, which can be expressed by the following formula:
E1=A1×V1
E2=A2×V2 - On the other hand, the flow rate F on the secondary side fluid of the
evaporator 54, the temperature difference between entry and exit (T2−T1), and the specific heat can be expressed as follows:
H=F×(T2−T1)×C - It is confirmed whether or not the initially planned energy-saving effect is maintained by comparing the thus periodically determined current values and the characteristics shown in
FIG. 14 . An energy-saving effect over the planned value leads to a profit. If under the planned value, the machines are inspected, and when a malfunction is found, recovery of the functions is tried through maintenance or repair. As is evident fromFIG. 14 , adoption of inverter driving permitted energy curtailment corresponding to the shadowed portion in a case of a cooling water temperature of 32° C. as compared with the case without an inverter. - The energy saving effect by installing the energy-saving equipment such as co-generator and inverter driven refrigerator varies with the load of the energy-saving equipment, as shown in
FIG. 12 orFIG. 14 . The energy consumption of the energy saving object facilities, such as the production facility, increase with the load, such as the production quantity of the object facilities, for example, as shown bycurve 61 inFIG. 15 . On the other hand, the energy consumption of the energy saving object facilities after taking the energy-saving measures is decreased, for example, as shown bycurve 62 inFIG. 15 . The energy saving effect of the example ofFIG. 15 corresponds to the hatched region, as shown, and increases with an increase in the production quantities of the production facility. Therefore, when the overall energy saving effect of the energy saving object facilities is evaluated, it should be compared with the energy consumption of the same load and production quantities of the energy saving object facilities. Similarly, the energy consumption of the energy saving object facilities vary with attribute data such as operating hours or operating rate, weather condition, (temperature, humidity), season, and day or night. Therefore, for calculation of the energy-saving effect comparison should be made of energy consumption with same condition of the attribute data before and after taking the energy-saving measures. - Similarly, the status of the other energy-saving facilities and equipments is monitored on the basis of the measured data thereof, and if the result is under the planned value, the machines are inspected. If a malfunction is found, recovery of functions is tried through maintenance or repair.
- The present invention is not limited to the above-mentioned form of contract, but any other form may be adopted. While a case where the energy service enterprise is responsible for payment of all the costs for energy-saving measures has been described above, the costs may be shared at certain ratios with the customer. The customer may bear all the costs. In these cases, the share of the energy service enterprise should naturally be approximately adjusted.
- The contract may take another form of assuring an energy-saving effect on the basis of the plan of energy-saving measures, and receiving payment of a certain amount of money from the customer in compensation for assessment. More specifically, the energy service enterprise or a related organization drafts a plan of energy-saving measures, assures a quantity of energy curtailment, under certain conditions, available when installing energy-saving facilities in accordance with the planned measures, measures the energy consumption after taking the energy-saving measures, determines the difference of the measured value from the energy consumption before taking the energy-saving measures previously stored in the database, and confirms the assured quantity of curtailment periodically. When the assured value is satisfied, the energy service enterprise can receive compensation in a fixed amount or at a fixed rate in response to the amount of curtailed energy cost as a reward for successful achievement. When contributing investment funds, this enables the customer to introduce energy-saving facilities with confidence.
- The certain conditions for assurance cover factors which may exert an important influence on the curtailment effect of the energy consumption such as the operating rate or operating hours of the facilities to which the energy-saving measures are applied energy-saving object facilities, and the operating conditions of the energy-saving object facilities (production quantity, batch processing frequency, etc.). The certain conditions may have ranges. Weather conditions (temperature, humidity), which exert an important effect on the energy-saving effect, can be coped with by using past data under the same conditions.
- When the quantity of energy curtailment is under the assured value, the energy service enterprise performs maintenance of the energy-saving facilities so as to satisfy the assured value, or improves the energy-saving facilities. In this case, the contract should set forth that the energy service enterprise receives a compensation in response to the quantity of energy curtailment in excess of the assured value.
- According to the present invention, as described above, it is possible to easily take energy-saving measures.
Claims (2)
1. An energy service business system comprising:
a database which stores past data about an energy consumption of at least one of a production facility and an utility facility utilizing cold or warm heat energy before taking energy-saving measures by installing energy-saving equipment;
measuring means which measures present data of the energy consumption of the at least one of the production facility and the utility facility after taking the energy-saving measures; and
calculating means which calculates energy curtailment quantities of the at least one of the production facility and the utility facility before and after taking the energy-saving measures by installing the energy-saving equipment;
wherein the past data in the database are stored in a form correlated with data of a production quantity of the production facility before taking the energy-saving measures;
wherein the measuring means measures the present data of the energy consumption of the at least one of the production facility and the utility facility after taking the energy-saving measures together with data of the production quantity; and
the calculating means retrieves the past data having production quantity data within a set allowable range corresponding to the measured present data having production quantity data for the at least one of the production facility and the utility facility, and calculates the energy curtailment quantities by comparing the retrieved past data having production quantity data and the measured present data having the production quantity data.
2. An energy service business system according to claim 1 , wherein the calculating means retrieves a plurality of the past data corresponding to a plurality of production quantities approximating the measured production quantity, performs calculations for estimating past data corresponding to the measured production quantity from the plurality of past data, and calculates the energy curtailment quantities by comparing the thus calculated past estimated data and the present data.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US11/583,883 US20070094043A1 (en) | 2000-07-14 | 2006-10-20 | Energy service business method and system |
Applications Claiming Priority (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000214142A JP4523124B2 (en) | 2000-07-14 | 2000-07-14 | Energy service business system |
JP2000-214142 | 2000-07-14 | ||
US09/843,736 US7130832B2 (en) | 2000-07-14 | 2001-04-30 | Energy service business method and system |
US11/583,883 US20070094043A1 (en) | 2000-07-14 | 2006-10-20 | Energy service business method and system |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US09/843,736 Continuation-In-Part US7130832B2 (en) | 2000-07-14 | 2001-04-30 | Energy service business method and system |
Publications (1)
Publication Number | Publication Date |
---|---|
US20070094043A1 true US20070094043A1 (en) | 2007-04-26 |
Family
ID=18709780
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US09/843,736 Expired - Lifetime US7130832B2 (en) | 2000-07-14 | 2001-04-30 | Energy service business method and system |
US11/583,883 Abandoned US20070094043A1 (en) | 2000-07-14 | 2006-10-20 | Energy service business method and system |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US09/843,736 Expired - Lifetime US7130832B2 (en) | 2000-07-14 | 2001-04-30 | Energy service business method and system |
Country Status (2)
Country | Link |
---|---|
US (2) | US7130832B2 (en) |
JP (1) | JP4523124B2 (en) |
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090228405A1 (en) * | 2008-03-07 | 2009-09-10 | Teresa Lopez | Apparatus and Method for Determining and Applying an Energy Savings to a Financial Transaction |
US20090228320A1 (en) * | 2008-03-07 | 2009-09-10 | Teresa Lopez | Apparatus, System, and Method for Quantifying Bundling, and Applying Credits and Incentives to Financial Transactions |
US20090228406A1 (en) * | 2008-03-07 | 2009-09-10 | Teresa Lopez | Apparatus, System, and Method for Quantifying Energy Usage and Savings |
US20090234803A1 (en) * | 2008-03-11 | 2009-09-17 | Continental Electrical Construction Company, Llc | Keyword search of business information system |
US20100217631A1 (en) * | 2009-02-23 | 2010-08-26 | International Business Machines Corporation | Conservation modeling engine framework |
US20110213508A1 (en) * | 2010-02-26 | 2011-09-01 | International Business Machines Corporation | Optimizing power consumption by dynamic workload adjustment |
US20120084030A1 (en) * | 2009-04-10 | 2012-04-05 | Omron Corporation | Energy monitoring device and control method therefor, and energy monitoring program |
US20120095708A1 (en) * | 2010-10-14 | 2012-04-19 | Yamatake Corporation | Total energy quantity controlling device and method |
US20120221163A1 (en) * | 2007-08-28 | 2012-08-30 | Forbes Jr Joseph W | Systems and methods for determining and utilizing customer energy profiles for load control for individual structures, devices, and aggregation of same |
US20140310718A1 (en) * | 2011-11-08 | 2014-10-16 | Bull Sas | Method, computer program and device for allocating computer resources of a cluster for executing a task submitted to said cluster |
US20150088327A1 (en) * | 2013-09-26 | 2015-03-26 | Azbil Corporation | Energy savings forecasting method and device |
US10303194B2 (en) | 2007-08-28 | 2019-05-28 | Causam Energy, Inc | System, method, and apparatus for actively managing consumption of electric power supplied by one or more electric power grid operators |
US10394268B2 (en) | 2007-08-28 | 2019-08-27 | Causam Energy, Inc. | Method and apparatus for actively managing consumption of electric power over an electric power grid |
US10396592B2 (en) | 2007-08-28 | 2019-08-27 | Causam Energy, Inc. | System and method for estimating and providing dispatchable operating reserve energy capacity through use of active load management |
CN112119421A (en) * | 2018-07-03 | 2020-12-22 | 三菱动力株式会社 | Upgrade evaluation method and upgrade evaluation device |
US11676079B2 (en) | 2009-05-08 | 2023-06-13 | Causam Enterprises, Inc. | System and method for generating and providing dispatchable operating reserve energy capacity through use of active load management |
WO2023128001A1 (en) * | 2021-12-29 | 2023-07-06 | 주식회사 테라플랫폼 | Relay system for energy efficiency project |
Families Citing this family (131)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6868293B1 (en) * | 2000-09-28 | 2005-03-15 | Itron, Inc. | System and method for energy usage curtailment |
JP4238483B2 (en) * | 2001-03-12 | 2009-03-18 | 株式会社日立製作所 | Electronics rental system |
US6892546B2 (en) * | 2001-05-03 | 2005-05-17 | Emerson Retail Services, Inc. | System for remote refrigeration monitoring and diagnostics |
US6668240B2 (en) | 2001-05-03 | 2003-12-23 | Emerson Retail Services Inc. | Food quality and safety model for refrigerated food |
JP3972247B2 (en) * | 2002-05-10 | 2007-09-05 | 横河電機株式会社 | Energy saving service system |
US20040059691A1 (en) * | 2002-09-20 | 2004-03-25 | Higgins Robert L. | Method for marketing energy-use optimization and retrofit services and devices |
US6889173B2 (en) | 2002-10-31 | 2005-05-03 | Emerson Retail Services Inc. | System for monitoring optimal equipment operating parameters |
BRPI0413003A (en) * | 2003-07-28 | 2006-09-26 | Siemens Ag | method and system to reduce energy costs in an industrially operated facility |
DE10334397A1 (en) * | 2003-07-28 | 2005-03-10 | Siemens Ag | Reducing energy costs in an industrially operated facility e.g. paper and pulp production involves providing for energy flows of the facility, from its purchase, its conversion in secondary process and its consumption in core process |
US8560476B2 (en) * | 2003-08-26 | 2013-10-15 | The Trustees Of Columbia University In The City Of New York | Martingale control of production for optimal profitability of oil and gas fields |
US7412842B2 (en) | 2004-04-27 | 2008-08-19 | Emerson Climate Technologies, Inc. | Compressor diagnostic and protection system |
US7979166B2 (en) * | 2004-04-28 | 2011-07-12 | Sharp Kabushiki Kaisha | Generation facility management system |
JP2006018629A (en) * | 2004-07-02 | 2006-01-19 | Raito System Partner:Kk | Power consumption reduction amount management system, power consumption reduction amount distribution method and program therefor |
US7275377B2 (en) | 2004-08-11 | 2007-10-02 | Lawrence Kates | Method and apparatus for monitoring refrigerant-cycle systems |
JP4945077B2 (en) * | 2004-12-03 | 2012-06-06 | シャープ株式会社 | Power storage equipment management system |
DE602006008581D1 (en) * | 2005-02-17 | 2009-10-01 | Panasonic Corp | PROCESS FOR DETERMINING ASSEMBLY CONDITIONS, DEVICE FOR DETERMINING ASSEMBLY CONDITIONS AND ASSEMBLING DEVICE |
JP2006350542A (en) * | 2005-06-14 | 2006-12-28 | Hitachi Ltd | Energy saving water distribution support system |
JP4841185B2 (en) * | 2005-06-30 | 2011-12-21 | 中国電力株式会社 | Investment effect evaluation system and method for instantaneous voltage drop countermeasure device |
US20070028632A1 (en) * | 2005-08-03 | 2007-02-08 | Mingsheng Liu | Chiller control system and method |
US9310098B2 (en) | 2006-01-27 | 2016-04-12 | Emerson Electric Co. | Water heater control using external temperature sensor |
US9151516B2 (en) * | 2006-01-27 | 2015-10-06 | Emerson Electric Co. | Smart energy controlled water heater |
US9188363B2 (en) | 2006-01-27 | 2015-11-17 | Emerson Electric Co. | Smart energy controlled water heater |
US7392115B2 (en) * | 2006-03-01 | 2008-06-24 | Honeywell International Inc. | Characterization of utility demand using utility demand footprint |
US20120036091A1 (en) * | 2006-06-12 | 2012-02-09 | Cook Kenneth W | System and method for automated, range-based irrigation |
US8590325B2 (en) | 2006-07-19 | 2013-11-26 | Emerson Climate Technologies, Inc. | Protection and diagnostic module for a refrigeration system |
US20080027883A1 (en) * | 2006-07-25 | 2008-01-31 | Earth Utility Pty Ltd | Utilities provision system and method |
KR101414917B1 (en) * | 2006-09-04 | 2014-07-04 | 메이지 세이카 파루마 가부시키가이샤 | Method for producing optically active aminophosphinylbutanoic acid |
US20080216494A1 (en) | 2006-09-07 | 2008-09-11 | Pham Hung M | Compressor data module |
WO2008039759A2 (en) * | 2006-09-25 | 2008-04-03 | Intelligent Management Systems Corporation | System and method for resource management |
US8884203B2 (en) | 2007-05-03 | 2014-11-11 | Orion Energy Systems, Inc. | Lighting systems and methods for displacing energy consumption using natural lighting fixtures |
US8376600B2 (en) | 2007-06-29 | 2013-02-19 | Orion Energy Systems, Inc. | Lighting device |
US8406937B2 (en) | 2008-03-27 | 2013-03-26 | Orion Energy Systems, Inc. | System and method for reducing peak and off-peak electricity demand by monitoring, controlling and metering high intensity fluorescent lighting in a facility |
US7638743B2 (en) * | 2007-06-29 | 2009-12-29 | Orion Energy Systems, Inc. | Method and system for controlling a lighting system |
US8450670B2 (en) | 2007-06-29 | 2013-05-28 | Orion Energy Systems, Inc. | Lighting fixture control systems and methods |
US8344665B2 (en) | 2008-03-27 | 2013-01-01 | Orion Energy Systems, Inc. | System and method for controlling lighting |
US8626643B2 (en) * | 2007-05-03 | 2014-01-07 | Orion Energy Systems, Inc. | System and method for a utility financial model |
US8866582B2 (en) | 2009-09-04 | 2014-10-21 | Orion Energy Systems, Inc. | Outdoor fluorescent lighting fixtures and related systems and methods |
US8445826B2 (en) | 2007-06-29 | 2013-05-21 | Orion Energy Systems, Inc. | Outdoor lighting systems and methods for wireless network communications |
US8476565B2 (en) | 2007-06-29 | 2013-07-02 | Orion Energy Systems, Inc. | Outdoor lighting fixtures control systems and methods |
US8586902B2 (en) | 2007-06-29 | 2013-11-19 | Orion Energy Systems, Inc. | Outdoor lighting fixture and camera systems |
US8729446B2 (en) | 2007-06-29 | 2014-05-20 | Orion Energy Systems, Inc. | Outdoor lighting fixtures for controlling traffic lights |
US20090037142A1 (en) | 2007-07-30 | 2009-02-05 | Lawrence Kates | Portable method and apparatus for monitoring refrigerant-cycle systems |
US7908117B2 (en) | 2007-08-03 | 2011-03-15 | Ecofactor, Inc. | System and method for using a network of thermostats as tool to verify peak demand reduction |
US8019567B2 (en) | 2007-09-17 | 2011-09-13 | Ecofactor, Inc. | System and method for evaluating changes in the efficiency of an HVAC system |
US7848900B2 (en) * | 2008-09-16 | 2010-12-07 | Ecofactor, Inc. | System and method for calculating the thermal mass of a building |
US9140728B2 (en) | 2007-11-02 | 2015-09-22 | Emerson Climate Technologies, Inc. | Compressor sensor module |
US8249902B2 (en) * | 2008-02-29 | 2012-08-21 | Solarcity Corporation | Methods of processing information in solar energy system |
US7904382B2 (en) * | 2008-03-11 | 2011-03-08 | Solarcity Corporation | Methods for financing renewable energy systems |
US7925552B2 (en) * | 2008-03-13 | 2011-04-12 | Solarcity Corporation | Renewable energy system monitor |
US20090234685A1 (en) * | 2008-03-13 | 2009-09-17 | Ben Tarbell | Renewable energy system maintenance business model |
WO2009117741A1 (en) * | 2008-03-21 | 2009-09-24 | The Trustees Of Columbia University In The City Of New York | Decision support control centers |
WO2009117742A1 (en) * | 2008-03-21 | 2009-09-24 | The Trustees Of Columbia University In The City Of New York | Methods and systems of determining the effectiveness of capital improvement projects |
US8010237B2 (en) | 2008-07-07 | 2011-08-30 | Ecofactor, Inc. | System and method for using ramped setpoint temperature variation with networked thermostats to improve efficiency |
US20100010939A1 (en) * | 2008-07-12 | 2010-01-14 | David Arfin | Renewable energy system business tuning |
US8180492B2 (en) | 2008-07-14 | 2012-05-15 | Ecofactor, Inc. | System and method for using a networked electronic device as an occupancy sensor for an energy management system |
US20100023337A1 (en) * | 2008-07-22 | 2010-01-28 | Eliot Maxwell Case | Local Power Generation Business Method |
US20100057480A1 (en) * | 2008-08-27 | 2010-03-04 | David Arfin | Energy Services |
US20100057544A1 (en) * | 2008-09-03 | 2010-03-04 | Ben Tarbell | Renewable energy employee and employer group discounting |
US9002761B2 (en) | 2008-10-08 | 2015-04-07 | Rey Montalvo | Method and system for automatically adapting end user power usage |
WO2010042200A1 (en) * | 2008-10-08 | 2010-04-15 | Rey Montalvo | Method and system for fully automated energy curtailment |
WO2010096783A1 (en) | 2009-02-20 | 2010-08-26 | The Trustees Of Columbia University In The City Of New York | Dynamic contingency avoidance and mitigation system |
US8498753B2 (en) | 2009-05-08 | 2013-07-30 | Ecofactor, Inc. | System, method and apparatus for just-in-time conditioning using a thermostat |
US8285603B2 (en) * | 2009-05-11 | 2012-10-09 | Revolution Environmental Llc | Method and system for providing recommendations as part of a home energy audit |
US8740100B2 (en) | 2009-05-11 | 2014-06-03 | Ecofactor, Inc. | System, method and apparatus for dynamically variable compressor delay in thermostat to reduce energy consumption |
US8596550B2 (en) | 2009-05-12 | 2013-12-03 | Ecofactor, Inc. | System, method and apparatus for identifying manual inputs to and adaptive programming of a thermostat |
US8725625B2 (en) | 2009-05-28 | 2014-05-13 | The Trustees Of Columbia University In The City Of New York | Capital asset planning system |
EP2435917B1 (en) | 2009-05-29 | 2021-11-10 | Emerson Climate Technologies Retail Solutions, Inc. | System and method for monitoring and evaluating equipment operating parameter modifications |
US8600556B2 (en) | 2009-06-22 | 2013-12-03 | Johnson Controls Technology Company | Smart building manager |
US10739741B2 (en) | 2009-06-22 | 2020-08-11 | Johnson Controls Technology Company | Systems and methods for detecting changes in energy usage in a building |
US11269303B2 (en) | 2009-06-22 | 2022-03-08 | Johnson Controls Technology Company | Systems and methods for detecting changes in energy usage in a building |
US9196009B2 (en) * | 2009-06-22 | 2015-11-24 | Johnson Controls Technology Company | Systems and methods for detecting changes in energy usage in a building |
US9412082B2 (en) * | 2009-12-23 | 2016-08-09 | General Electric Company | Method and system for demand response management in a network |
US8630882B2 (en) * | 2010-01-13 | 2014-01-14 | International Business Machines Corporation | Implementing an optimal intelligent enterprise architecture via virtualization, information intelligence, social computing and green environmental considerations |
WO2011106511A1 (en) | 2010-02-24 | 2011-09-01 | The Trustees Of Columbia University In The City Of New York | Metric monitoring and financial validation system for tracking performance of improvement to an infrastructure |
US8556188B2 (en) | 2010-05-26 | 2013-10-15 | Ecofactor, Inc. | System and method for using a mobile electronic device to optimize an energy management system |
US10584890B2 (en) | 2010-05-26 | 2020-03-10 | Ecofactor, Inc. | System and method for using a mobile electronic device to optimize an energy management system |
WO2012009724A1 (en) | 2010-07-16 | 2012-01-19 | The Trustees Of Columbia University In The City Of New York | Machine learning for power grids |
US8090477B1 (en) | 2010-08-20 | 2012-01-03 | Ecofactor, Inc. | System and method for optimizing use of plug-in air conditioners and portable heaters |
US8560134B1 (en) | 2010-09-10 | 2013-10-15 | Kwangduk Douglas Lee | System and method for electric load recognition from centrally monitored power signal and its application to home energy management |
JPWO2012050208A1 (en) * | 2010-10-15 | 2014-02-24 | 三洋電機株式会社 | Power management system |
JP2012088910A (en) * | 2010-10-19 | 2012-05-10 | Yokogawa Electric Corp | Energy saving effect calculation device |
JP5679847B2 (en) * | 2011-02-04 | 2015-03-04 | 株式会社東芝 | Energy management system and energy management method |
CA2934860C (en) | 2011-02-28 | 2018-07-31 | Emerson Electric Co. | Residential solutions hvac monitoring and diagnosis |
JP5777923B2 (en) * | 2011-04-04 | 2015-09-09 | 株式会社 Jcサービス | Resource-saving / energy-saving evaluation operation system |
US20130085885A1 (en) * | 2011-09-29 | 2013-04-04 | Neozyte | System and method for a photovoltaic plant market exchange |
US8751291B2 (en) * | 2012-01-05 | 2014-06-10 | General Electric Comany | Economic analysis of grid infrastructure |
US8964338B2 (en) | 2012-01-11 | 2015-02-24 | Emerson Climate Technologies, Inc. | System and method for compressor motor protection |
CN103457753A (en) * | 2012-05-31 | 2013-12-18 | 成都勤智数码科技股份有限公司 | Implementing method for energy consumption control in operation and maintenance guarantees |
US9390388B2 (en) | 2012-05-31 | 2016-07-12 | Johnson Controls Technology Company | Systems and methods for measuring and verifying energy usage in a building |
US10048706B2 (en) | 2012-06-14 | 2018-08-14 | Ecofactor, Inc. | System and method for optimizing use of individual HVAC units in multi-unit chiller-based systems |
CA2884093A1 (en) * | 2012-09-12 | 2014-03-20 | Heatcraft Refrigeration Products Llc | Systems, methods, and apparatus for preventing condensation in refrigerated display cases |
US9310439B2 (en) | 2012-09-25 | 2016-04-12 | Emerson Climate Technologies, Inc. | Compressor having a control and diagnostic module |
AU2012268776A1 (en) * | 2012-12-20 | 2014-07-10 | Embertec Pty Ltd | Electrical device installation improvement |
US9785902B1 (en) * | 2013-02-06 | 2017-10-10 | Leidos, Inc. | Computer-implemented engineering review of energy consumption by equipment |
WO2014144446A1 (en) | 2013-03-15 | 2014-09-18 | Emerson Electric Co. | Hvac system remote monitoring and diagnosis |
US9803902B2 (en) | 2013-03-15 | 2017-10-31 | Emerson Climate Technologies, Inc. | System for refrigerant charge verification using two condenser coil temperatures |
US9551504B2 (en) | 2013-03-15 | 2017-01-24 | Emerson Electric Co. | HVAC system remote monitoring and diagnosis |
US9765979B2 (en) | 2013-04-05 | 2017-09-19 | Emerson Climate Technologies, Inc. | Heat-pump system with refrigerant charge diagnostics |
JP6166946B2 (en) * | 2013-05-08 | 2017-07-19 | 大成建設株式会社 | Profitability determination method, profitability determination device, and profitability determination program |
JP6169964B2 (en) * | 2013-12-18 | 2017-07-26 | 京セラ株式会社 | Energy management system, energy management apparatus, and energy management method |
WO2015151011A1 (en) * | 2014-04-02 | 2015-10-08 | Koninklijke Philips N.V. | System and method for providing efficient lifecycle energy services |
JP6374702B2 (en) * | 2014-05-21 | 2018-08-15 | アズビル株式会社 | Energy saving effect calculation method and apparatus |
JP6367082B2 (en) * | 2014-10-30 | 2018-08-01 | 横河電機株式会社 | Energy saving potential evaluation system and energy saving potential evaluation method |
US9910076B2 (en) | 2014-11-17 | 2018-03-06 | Elspec Engineering Ltd. | Method and system for analysis of energy savings in an electrical network |
TWI539399B (en) * | 2015-01-14 | 2016-06-21 | The charging method and charging method of lighting equipment | |
TWI549088B (en) * | 2015-03-19 | 2016-09-11 | Electricity charging method | |
JP5944552B1 (en) * | 2015-04-13 | 2016-07-05 | 純 山内 | Equipment cost calculation system, equipment cost calculation method and program |
KR101735705B1 (en) * | 2015-09-22 | 2017-05-15 | 주식회사 에코시안 | Method and apparatus for evaluation for energy efficiency of building |
EP3168805A1 (en) * | 2015-11-11 | 2017-05-17 | Enerlife S.R.L. | Method and system for controlling energy consumption values |
US10261838B2 (en) | 2016-08-11 | 2019-04-16 | General Electric Company | Method and device for allocating resources in a system |
JP6397086B2 (en) * | 2017-06-29 | 2018-09-26 | 京セラ株式会社 | Equipment management device and equipment management method |
US11678615B2 (en) | 2018-01-11 | 2023-06-20 | Lancium Llc | Method and system for dynamic power delivery to a flexible growcenter using unutilized energy sources |
KR102210463B1 (en) | 2018-07-06 | 2021-02-01 | 한국에너지기술연구원 | Energy Trade System |
US11016553B2 (en) | 2018-09-14 | 2021-05-25 | Lancium Llc | Methods and systems for distributed power control of flexible datacenters |
US11025060B2 (en) | 2018-09-14 | 2021-06-01 | Lancium Llc | Providing computational resource availability based on power-generation signals |
US11031787B2 (en) | 2018-09-14 | 2021-06-08 | Lancium Llc | System of critical datacenters and behind-the-meter flexible datacenters |
US10873211B2 (en) | 2018-09-14 | 2020-12-22 | Lancium Llc | Systems and methods for dynamic power routing with behind-the-meter energy storage |
US11031813B2 (en) | 2018-10-30 | 2021-06-08 | Lancium Llc | Systems and methods for auxiliary power management of behind-the-meter power loads |
US11128165B2 (en) | 2019-02-25 | 2021-09-21 | Lancium Llc | Behind-the-meter charging station with availability notification |
PH12021552340A1 (en) * | 2019-03-29 | 2022-08-15 | Daikin Ind Ltd | Maintenance contract fee calculation system |
WO2020227811A1 (en) | 2019-05-15 | 2020-11-19 | Upstream Data Inc. | Portable blockchain mining system and methods of use |
CN110472837B (en) * | 2019-07-24 | 2023-04-18 | 嘉兴市澳优节能评估服务有限公司 | Energy consumption calculation method applied to energy saving evaluation |
US11868106B2 (en) | 2019-08-01 | 2024-01-09 | Lancium Llc | Granular power ramping |
US11397999B2 (en) | 2019-08-01 | 2022-07-26 | Lancium Llc | Modifying computing system operations based on cost and power conditions |
JP6974757B2 (en) | 2019-09-30 | 2021-12-01 | ダイキン工業株式会社 | Information processing methods, information processing devices, and programs |
US11016458B2 (en) | 2019-10-28 | 2021-05-25 | Lancium Llc | Methods and systems for adjusting power consumption based on dynamic power option agreement |
CN110783917A (en) * | 2019-11-05 | 2020-02-11 | 国网江苏省电力有限公司镇江供电分公司 | Configuration method of multi-energy energy hub with new energy consumption |
US11042948B1 (en) | 2020-02-27 | 2021-06-22 | Lancium Llc | Computing component arrangement based on ramping capabilities |
CA3076653A1 (en) | 2020-03-21 | 2021-09-21 | Upstream Data Inc. | Portable blockchain mining systems and methods of use |
CN111784188A (en) * | 2020-07-14 | 2020-10-16 | 中国南方电网有限责任公司 | Comprehensive energy service business market clearing method based on electric power market |
CA3189144A1 (en) | 2020-08-14 | 2022-02-17 | Andrew GRIMSHAW | Power aware scheduling |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4399510A (en) * | 1979-04-03 | 1983-08-16 | Nuclear Systems, Inc. | System for monitoring utility usage |
US5566084A (en) * | 1993-03-02 | 1996-10-15 | Cmar; Gregory | Process for identifying patterns of electric energy effects of proposed changes, and implementing such changes in the facility to conserve energy |
US5758331A (en) * | 1994-08-15 | 1998-05-26 | Clear With Computers, Inc. | Computer-assisted sales system for utilities |
US5762265A (en) * | 1995-10-06 | 1998-06-09 | Matsushita Electric Industrial Co., Ltd. | Air-conditioning control unit |
US5924486A (en) * | 1997-10-29 | 1999-07-20 | Tecom, Inc. | Environmental condition control and energy management system and method |
US5962989A (en) * | 1995-01-17 | 1999-10-05 | Negawatt Technologies Inc. | Energy management control system |
US6105000A (en) * | 1996-10-16 | 2000-08-15 | Aquila Risk Management Corporation | Financial rebate program for utilities based on degree days |
US6324860B1 (en) * | 1997-10-24 | 2001-12-04 | Ebara Corporation | Dehumidifying air-conditioning system |
US6424871B1 (en) * | 1996-10-31 | 2002-07-23 | Ebara Corporation | Rotating machine integrated with controller, and inverter |
US6535859B1 (en) * | 1999-12-03 | 2003-03-18 | Ultrawatt Energy System, Inc | System and method for monitoring lighting systems |
US6772052B1 (en) * | 1998-04-07 | 2004-08-03 | It & Process As | System for controlling power consumption at a user of electric power |
US6785592B1 (en) * | 1999-07-16 | 2004-08-31 | Perot Systems Corporation | System and method for energy management |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2093615A (en) * | 1981-01-28 | 1982-09-02 | Atkins Patrick Ralph | Home energy saving computer |
AU6213900A (en) | 1999-07-16 | 2001-02-05 | Patrick T. Golden | System and method for energy management |
JP4488592B2 (en) * | 2000-02-15 | 2010-06-23 | 三菱電機株式会社 | Equipment management device, equipment management method |
JP2001282889A (en) * | 2000-03-30 | 2001-10-12 | Tokyo Gas Co Ltd | Energy saving service support system and energy saving service price calculation method |
-
2000
- 2000-07-14 JP JP2000214142A patent/JP4523124B2/en not_active Expired - Fee Related
-
2001
- 2001-04-30 US US09/843,736 patent/US7130832B2/en not_active Expired - Lifetime
-
2006
- 2006-10-20 US US11/583,883 patent/US20070094043A1/en not_active Abandoned
Patent Citations (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4399510A (en) * | 1979-04-03 | 1983-08-16 | Nuclear Systems, Inc. | System for monitoring utility usage |
US5566084A (en) * | 1993-03-02 | 1996-10-15 | Cmar; Gregory | Process for identifying patterns of electric energy effects of proposed changes, and implementing such changes in the facility to conserve energy |
US5758331A (en) * | 1994-08-15 | 1998-05-26 | Clear With Computers, Inc. | Computer-assisted sales system for utilities |
US6169979B1 (en) * | 1994-08-15 | 2001-01-02 | Clear With Computers, Inc. | Computer-assisted sales system for utilities |
US5962989A (en) * | 1995-01-17 | 1999-10-05 | Negawatt Technologies Inc. | Energy management control system |
US5762265A (en) * | 1995-10-06 | 1998-06-09 | Matsushita Electric Industrial Co., Ltd. | Air-conditioning control unit |
US6105000A (en) * | 1996-10-16 | 2000-08-15 | Aquila Risk Management Corporation | Financial rebate program for utilities based on degree days |
US6424871B1 (en) * | 1996-10-31 | 2002-07-23 | Ebara Corporation | Rotating machine integrated with controller, and inverter |
US6324860B1 (en) * | 1997-10-24 | 2001-12-04 | Ebara Corporation | Dehumidifying air-conditioning system |
US5924486A (en) * | 1997-10-29 | 1999-07-20 | Tecom, Inc. | Environmental condition control and energy management system and method |
US6216956B1 (en) * | 1997-10-29 | 2001-04-17 | Tocom, Inc. | Environmental condition control and energy management system and method |
US6772052B1 (en) * | 1998-04-07 | 2004-08-03 | It & Process As | System for controlling power consumption at a user of electric power |
US6785592B1 (en) * | 1999-07-16 | 2004-08-31 | Perot Systems Corporation | System and method for energy management |
US6535859B1 (en) * | 1999-12-03 | 2003-03-18 | Ultrawatt Energy System, Inc | System and method for monitoring lighting systems |
Cited By (42)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11022995B2 (en) | 2007-08-28 | 2021-06-01 | Causam Enterprises, Inc. | Method and apparatus for actively managing consumption of electric power over an electric power grid |
US11025057B2 (en) | 2007-08-28 | 2021-06-01 | Causam Enterprises, Inc. | Systems and methods for determining and utilizing customer energy profiles for load control for individual structures, devices, and aggregation of same |
US11735915B2 (en) | 2007-08-28 | 2023-08-22 | Causam Enterprises, Inc. | System and method for estimating and providing dispatchable operating reserve energy capacity through use of active load management |
US11733726B2 (en) | 2007-08-28 | 2023-08-22 | Causam Enterprises, Inc. | System, method, and apparatus for actively managing consumption of electric power supplied by one or more electric power grid operators |
US11651295B2 (en) | 2007-08-28 | 2023-05-16 | Causam Enterprises, Inc. | Systems and methods for determining and utilizing customer energy profiles for load control for individual structures, devices, and aggregation of same |
US11650612B2 (en) | 2007-08-28 | 2023-05-16 | Causam Enterprises, Inc. | Method and apparatus for actively managing consumption of electric power over an electric power grid |
US11119521B2 (en) | 2007-08-28 | 2021-09-14 | Causam Enterprises, Inc. | System, method, and apparatus for actively managing consumption of electric power supplied by one or more electric power grid operators |
US11108263B2 (en) | 2007-08-28 | 2021-08-31 | Causam Enterprises, Inc. | System and method for estimating and providing dispatchable operating reserve energy capacity through use of active load management |
US20120221163A1 (en) * | 2007-08-28 | 2012-08-30 | Forbes Jr Joseph W | Systems and methods for determining and utilizing customer energy profiles for load control for individual structures, devices, and aggregation of same |
US9899836B2 (en) | 2007-08-28 | 2018-02-20 | Causam Energy, Inc. | Systems and methods for determining and utilizing customer energy profiles for load control for individual structures, devices, and aggregation of same |
US10985556B2 (en) | 2007-08-28 | 2021-04-20 | Causam Energy, Inc. | Systems and methods for determining and utilizing customer energy profiles for load control for individual structures, devices, and aggregation of same |
US10833504B2 (en) | 2007-08-28 | 2020-11-10 | Causam Energy, Inc. | Systems and methods for determining and utilizing customer energy profiles for load control for individual structures, devices, and aggregation of same |
US10396592B2 (en) | 2007-08-28 | 2019-08-27 | Causam Energy, Inc. | System and method for estimating and providing dispatchable operating reserve energy capacity through use of active load management |
US10394268B2 (en) | 2007-08-28 | 2019-08-27 | Causam Energy, Inc. | Method and apparatus for actively managing consumption of electric power over an electric power grid |
US10389115B2 (en) | 2007-08-28 | 2019-08-20 | Causam Energy, Inc. | Systems and methods for determining and utilizing customer energy profiles for load control for individual structures, devices, and aggregation of same |
US10303194B2 (en) | 2007-08-28 | 2019-05-28 | Causam Energy, Inc | System, method, and apparatus for actively managing consumption of electric power supplied by one or more electric power grid operators |
US10116134B2 (en) | 2007-08-28 | 2018-10-30 | Causam Energy, Inc. | Systems and methods for determining and utilizing customer energy profiles for load control for individual structures, devices, and aggregation of same |
US9177323B2 (en) * | 2007-08-28 | 2015-11-03 | Causam Energy, Inc. | Systems and methods for determining and utilizing customer energy profiles for load control for individual structures, devices, and aggregation of same |
US20090228405A1 (en) * | 2008-03-07 | 2009-09-10 | Teresa Lopez | Apparatus and Method for Determining and Applying an Energy Savings to a Financial Transaction |
US20090228320A1 (en) * | 2008-03-07 | 2009-09-10 | Teresa Lopez | Apparatus, System, and Method for Quantifying Bundling, and Applying Credits and Incentives to Financial Transactions |
US20090228406A1 (en) * | 2008-03-07 | 2009-09-10 | Teresa Lopez | Apparatus, System, and Method for Quantifying Energy Usage and Savings |
US8266076B2 (en) | 2008-03-07 | 2012-09-11 | Eqs, Inc. | Apparatus, system, and method for quantifying energy usage and savings |
US8412643B2 (en) | 2008-03-07 | 2013-04-02 | Eqs, Inc. | Apparatus, system, and method for quantifying, bundling, and applying credits and incentives to financial transactions |
US20090234803A1 (en) * | 2008-03-11 | 2009-09-17 | Continental Electrical Construction Company, Llc | Keyword search of business information system |
US9098820B2 (en) * | 2009-02-23 | 2015-08-04 | International Business Machines Corporation | Conservation modeling engine framework |
US20100217631A1 (en) * | 2009-02-23 | 2010-08-26 | International Business Machines Corporation | Conservation modeling engine framework |
US8942934B2 (en) * | 2009-04-10 | 2015-01-27 | Omron Corporatin | Energy monitoring device and control method therefor, and energy monitoring program |
US20120084030A1 (en) * | 2009-04-10 | 2012-04-05 | Omron Corporation | Energy monitoring device and control method therefor, and energy monitoring program |
US11676079B2 (en) | 2009-05-08 | 2023-06-13 | Causam Enterprises, Inc. | System and method for generating and providing dispatchable operating reserve energy capacity through use of active load management |
US10175745B2 (en) | 2010-02-26 | 2019-01-08 | International Business Machines Corporation | Optimizing power consumption by dynamic workload adjustment |
US8489745B2 (en) | 2010-02-26 | 2013-07-16 | International Business Machines Corporation | Optimizing power consumption by dynamic workload adjustment |
US9501115B2 (en) | 2010-02-26 | 2016-11-22 | International Business Machines Corporation | Optimizing power consumption by dynamic workload adjustment |
US20110213508A1 (en) * | 2010-02-26 | 2011-09-01 | International Business Machines Corporation | Optimizing power consumption by dynamic workload adjustment |
US9008979B2 (en) * | 2010-10-14 | 2015-04-14 | Azbil Corporation | Total energy quantity controlling device and method |
US20120095708A1 (en) * | 2010-10-14 | 2012-04-19 | Yamatake Corporation | Total energy quantity controlling device and method |
US9880887B2 (en) * | 2011-11-08 | 2018-01-30 | Bull Sas | Method, computer program and device for allocating computer resources of a cluster for executing a task submitted to said cluster |
US20140310718A1 (en) * | 2011-11-08 | 2014-10-16 | Bull Sas | Method, computer program and device for allocating computer resources of a cluster for executing a task submitted to said cluster |
US20150088327A1 (en) * | 2013-09-26 | 2015-03-26 | Azbil Corporation | Energy savings forecasting method and device |
CN112119421A (en) * | 2018-07-03 | 2020-12-22 | 三菱动力株式会社 | Upgrade evaluation method and upgrade evaluation device |
US11835944B2 (en) * | 2018-07-03 | 2023-12-05 | Mitsubishi Heavy Industries, Ltd. | Upgrade evaluation method and upgrade evaluation device |
WO2023128001A1 (en) * | 2021-12-29 | 2023-07-06 | 주식회사 테라플랫폼 | Relay system for energy efficiency project |
US20240232907A1 (en) * | 2021-12-29 | 2024-07-11 | Tera Platform Inc. | Brokerage transaction system for energy efficiency business |
Also Published As
Publication number | Publication date |
---|---|
JP2002032438A (en) | 2002-01-31 |
US7130832B2 (en) | 2006-10-31 |
JP4523124B2 (en) | 2010-08-11 |
US20020007388A1 (en) | 2002-01-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7130832B2 (en) | Energy service business method and system | |
US6591620B2 (en) | Air conditioning equipment operation system and air conditioning equipment designing support system | |
US9286646B1 (en) | Method for managing centralized power generation with the aid of a digital computer | |
JP2003061245A (en) | Operation planning method for cogeneration apparatus | |
Ghaith et al. | Economics of household wind turbine grid-tied systems for five wind resource levels and alternative grid pricing rates | |
US20240213773A1 (en) | Systems and methods for peak-clipping and load-shifting energy storage dispatch control strategies for event-based demand response | |
JP2004110188A (en) | Energy service method and system | |
Eto et al. | Integrated analysis of demand-side programs | |
Rosenquist et al. | Life-cycle cost and payback period analysis for commercial unitary air conditioners | |
JP2002330541A (en) | Power plant operation and maintenance plan support system | |
Piette et al. | Technology assessment: thermal cool storage in commercial buildings | |
JP5132418B2 (en) | ESCO project implementation support device, ESCO project implementation support method, and ESCO project implementation support program | |
Comnes et al. | An integrated economic analysis of commercial thermal energy storage | |
Strachan et al. | The adoption of a decentralized energy technology: the case of UK engine cogeneration | |
Leger | Data Analytics for Electric Power and Energy Applications | |
Kurnik et al. | Combined Heat and Power Evaluation Protocol. The Uniform Methods Project: Methods for Determining Energy Efficiency Savings for Specific Measures | |
Newell et al. | Gross Avoidable Cost Rates for Existing Generation and Net Cost of New Entry for New Energy Efficiency | |
Badami et al. | Micro-multigeneration modelling and operational assessment for residential applications | |
Jackson et al. | Feasibility Analysis of Ice Thermal Energy Storage for a Chiller Plant Facility in Mediterranean Climate | |
Eskilsson | Energy flow mapping of a sports facility: Energy flow mapping and suitable key performance indicator formulation for Rocklunda sports facility | |
Younger | Using interval meter data for improved facility management | |
Fox | Can an Energy Autarky Private House be Economical? An Analysis Based on Germany | |
Costello et al. | An approach for evaluating utility-financed energy conservation programs The economic welfare model | |
Milligan et al. | Multi-Year Analysis of Renewable Energy Impacts in California: Results from the Renewable Portfolio Standards Integration Cost Analysis | |
Guyer et al. | Wet/dry cooling for cycling steam-electric plants. Final report |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: HITACHI, LTD., JAPAN Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:BANNAI, MASAAKI;CHIBA, JUNICHI;KUWABARA, KENICHI;AND OTHERS;REEL/FRAME:018752/0843;SIGNING DATES FROM 20061128 TO 20061208 |
|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |